Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Replace bridge for Vancouver’s Massey Tunnel could aid congestion
    December 21, 2015
    Opponents of a proposed 10-lane bridge near Vancouver, Canada, said the structure will encourage urban sprawl in a region that is already struggling with a booming population. The British Columbia provincial government recently opened the final round of public consultation for the planned 3.3km toll bridge likely to cost around US$2.54 billion.
  • Volvo wins on aggregate
    December 3, 2013
    In the Canadian city of Coquitlam, 3,628tonnes of glacial clay is being excavated every day across a 90hectare aggregate open-pit mine. LaFarge in North America is the largest diversified supplier of construction materials in the United States and Canada. For the last decade the company has used Greater Vancouver-based contractor, Vertex Excavating, to work across its 90hectare aggregate open-pit mine, exposing and transporting some of the best concrete aggregate material available on the market. Th
  • €1 billion tunnel for Genoa port
    March 6, 2024
    Construction is underway for Genoa’s €1 billion port tunnel.
  • New South Wales is seeking financial packers for WestConnex in Sydney
    June 19, 2015
    Investment bank Goldman Sachs will soon be sending out expressions of interest for backers to finance Australia’s biggest road deal, the three-stage WestConnex project to be rollout by the New South Wales government. According to a report by The Australian newspaper, initially around US$1.17 billion will be needed for the first phase of the Sydney toll road project. The first phase will likely cost between nearly $2.35 billion and $3.9 billion. Total cost of all three phases over 10 years could be as