Volvo wins on aggregate

In the Canadian city of Coquitlam, 3,628tonnes of glacial clay is being excavated every day across a 90hectare aggregate open-pit mine. LaFarge in North America is the largest diversified supplier of construction materials in the United States and Canada. For the last decade the company has used Greater Vancouver-based contractor, Vertex Excavating, to work across its 90hectare aggregate open-pit mine, exposing and transporting some of the best concrete aggregate material available on the market. Th
December 3, 2013 Read time: 4 mins
In the Canadian city of Coquitlam, 3,628tonnes of glacial clay is being excavated every day across a 90hectare aggregate open-pit mine.

3180 Lafarge in North America is the largest diversified supplier of construction materials in the United States and Canada. For the last decade the company has used Greater Vancouver-based contractor, Vertex Excavating, to work across its 90hectare aggregate open-pit mine, exposing and transporting some of the best concrete aggregate material available on the market.

The mine is located in the heart of the Pacific Northwest rain forest, where the average annual rainfall exceeds 1.27m. In the winter months it’s even more challenging with more than 1.52m of snow falling on mountainous land. Sunshine is scarce, and mountain roads are steep, with many paths on an incline of 20 degrees or higher.

“We are dealing with a lot of steep hills,” said Mike Pratchett, president of Vertex. “We also have to deal with almost 3.2km haul cycles and rain for 10 months of the year, resulting in muddy slippery slopes. You could say we have tough working conditions to contend with almost all year round.”

Vertex not only excavates clay and till at the mine but also clears the mountainside of logs, strips off the over-burden (that in some areas can be over 30m deep), controls mine waste management and works with the provincial and local authorities on water management and environmental issues, as well as road building.

With this amount of responsibility, Vertex needs reliable and efficient machinery it can count on. Volvo Construction Equipment (359 Volvo CE) machines help to expose daily more than 3,600tonnes of the best concrete aggregate. Vertex has no equipment in its fleet without the Volvo name on it. Its current taskforce consists of a pair of Volvo EC360B excavators, five Volvo A25D articulated haulers and a Tier 4-compliant Volvo EC380D crawler excavator.

One of the first of its kind to be delivered in North America, the Volvo EC380D has set the standard with its powerful Volvo D13Tier 4i engine rated at 208kW, maximum digging reach of 11.7m, maximum digging depth of 8.1m, and a maximum operating weight of 39.39tonnes. This heavy-duty production machine can be used for quarrying, road building, truck loading, mining construction, mass excavation, utility trenching and more.

“When the machine arrived, we added a few additional accessories to it, such as the larger 60-inch digging bucket, a hydraulic thumb and, because our contract calls for log clearing, we added the falling object protective structure (FOPS) to guard the cab from falling debris,” said Patchett. “It’s a tremendous machine, plenty of power, great stability, superior lighting and a cab full of creature comforts. Even in this till and clay that has been compacted for centuries, the excavator has allowed us to improve our cycle times.”

The Vertex team is pleased with the performance of its Volvo A25D articulated haulers. “My dad started his business using Volvo machines, and I’ve been around them all my working life,” commented Patchett. “When it came time to buy my own trucks, I wouldn’t consider any other brand. Because of the efficiency of the transmission retarders and exhaust brakes, we haven’t had to replace a single brake pad.”

“We do everything that our customer asks of us,” he added. “If we don’t have the equipment or the manpower, we’ll go and get it. A satisfied customer is a happy customer, and we have a terrific working relationship with Volvo CE’s dealer in the region – Great West Equipment. We do the daily maintenance, but when it comes to larger issues, we just give them a call and they’re here.”

For more information on companies in this article

Related Content

  • Volvo CE’s committed to innovation despite tough global market
    April 12, 2016
    Volvo Construction Equipment is said to be demonstrating its commitment to innovation despite the tough global sales market. The Swedish construction and quarrying equipment giant has this week unveiled its 90tonne Tier 4 Final/Stage IV complaint EC950E hydraulic crawler excavator – the biggest hydraulic crawler excavator it has ever made - and its 55tonne A60H articulated hauler. “I’m very pleased to say that on the first day of the show, we were taking order on this,” said Martin Weissburg, presiden
  • UAE mountain road construction complete
    January 5, 2017
    An eight year project to construct the highest road in the UAE is now complete, with key help having been provided by a fleet of Volvo CE machines The work was carried out by local contractor General Mechanic Company (GMC), with assistance from Volvo CE dealer FAMCO as well as Volvo CE itself and Volvo Trucks. The 36km road climbs 1,910m to its highest point in a mountain range and required the transportation of 5.5 million m3 of materials during its construction.
  • UK’s Liston Group brings a Volvo EC380E high reach machine
    April 10, 2017
    UK demolition contractor Liston Group’s latest fleet addition is a 51tonne Volvo EC380E high reach machine. The EC380E takes over from an EC360D high reach and is working alongside Volvo 25tonne excavators rigged for secondary demolition duties. Reliability and performance of the EC360D high reach machine played a role in the choice of the newer machine, which has the extra reach, designated by the ‘E’, said Liston’s managing director Tony McLean. In charge of the new EC380E is operator John Healy
  • Successfully manage inventory when you have multiple crushers on site
    June 11, 2021
    Optimised maintenance is a key competitive advantage for an aggregate producer