Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Crane deals arranged for Middle East customers
    December 15, 2017
    A series of key crane deals have been made across the Middle East. In Bahrain, Modern Mechanical, Electrical and Transporting (MMET) has placed an order for multiple Demag and Terex all-terrain cranes. MMET has an existing fleet of 15 Terex and Demag cranes. With its recent order, the company will expand its service capabilities with the addition of one Demag AC 60-3, two Demag AC 100-4Ls, one Demag AC 160-5, one Demag AC 220-5 and one Terex AC 40/2L. A major selling point for MMET was the
  • Peri formwork for Danish port link tunnel project
    November 29, 2013
    The Nordhavnsvej – Vej- og Tunnelentreprise (Nordhavnsvej) project is Copenhagen’s largest infrastructure project in the last 50 years. The 1.65km-long route will eventually link the Danish capital’s northern port area with the Helsingør motorway. It runs through a very densely built urban area, in parts at depths of up to 22m. One particular challenge regarding the execution was planning the course of the tunnel because the underground structure also crosses a very busy railway line.
  • Latest innovations in GPS and machine control
    February 22, 2012
    Modern satellite technology is making life easier for everyone on the construction site and in the office. Most major equipment manufacturers are now integrating GPS machine control systems into the design of excavators, bulldozers, pavers, and motor graders. For stake-less work it is a major component for automatic grading, surveying, and excavating systems, with contractors and construction companies using GPS machine control systems to improve operations.
  • Carry on Movin’ On - Michelin’s mobility event
    October 15, 2018
    Many of the great and the good in the global mobility sector gathered at this year’s Movin’ On event in Montreal. Measured regulation of technologies and safety issues were major themes, reports David Arminas Autonomous vehicles, platooning, smart intersections and safety – these were the talking points over two and half days of the Movin’ On event in Montreal. Everyone in the mobility sector is at the same point, trying to see what mobility will look like in the future. Apparent at the event was just