Moveable barrier cuts costs, aids motorists

Work on an award-winning US bridge was completed with savings and benefits to motorists through the help of an innovative barrier. The bridge replacement of US 31 over I-465 and Lick Creek in southern Indianapolis, state capital of Indiana, won the 2011 Honor Award from the American Council of Engineering Companies of Indiana. Stephen J. Christian & Associates of Indianapolis completed the design in less than nine months to allow Indiana Department of Transportation (INDOT) to take advantage of the favourab
February 20, 2012 Read time: 3 mins
The QuickChange Moveable Barrier from Barrier Systems

Work on an award-winning US bridge was completed with savings and benefits to motorists through the help of an innovative barrier.

The bridge replacement of US 31 over I-465 and Lick Creek in southern Indianapolis, state capital of Indiana, won the 2011 Honor Award from the 2853 American Council of Engineering Companies of Indiana.

Stephen J. Christian & Associates of Indianapolis completed the design in less than nine months to allow 2855 Indiana Department of Transportation (INDOT) to take advantage of the favourable bid conditions.

The work, completed late last year, called for replacement of the superstructure for the existing seven-span bridge. A new steel beam superstructure was selected in order to minimise the dead loads and utilise the existing substructure units.

US 31 is a busy urban arterial that carries over 54,000 vehicles per day, and it was apparent that the construction project would significantly impact traffic and cause major delays.

Lick Creek Bridge carries six lanes of traffic, with two through lanes in each direction and a ramp lane in both the northbound and southbound direction.

It was determined that the bridge was too narrow to maintain the current traffic flow during construction, and the original construction plans called for a temporary widening of the bridge that inflated the cost of construction to an estimated US$6 million.

Because US 31 has a directional traffic flow with a significantly higher volume in the northbound lanes during the morning peak and higher southbound volume in the evening peak, the concept of a moveable barrier was introduced.

The QuickChange Moveable Barrier (QMB) from 165 Barrier Systems, would physically separate the northbound and southbound traffic, but it could be quickly reconfigured several times per day to provide two lanes for peak traffic in each direction using a total of only three lanes in a 2/1, 2/2 configuration.

Because the bridge no longer had to be widened, the estimated project cost was revised to $4.8 million, a saving of $1.2 million over the original estimate.

"In addition to the cost savings, the moveable barrier provided benefits to motorists by maintaining the same number of traffic lanes throughout the entire project, and the surrounding neighborhoods benefited from the reduced impact to air quality that is typically created from traffic backups," says Barrier Systems.

"The project exceeded INDOT's original expectations in several categories including overall project cost and potential impact on the motoring public."

Related Content

  • Barrier innovation putting traffic safety and flow first
    April 3, 2014
    Cutting-edge barriers offering greater safety at the same time as limiting traffic disruption are proving in demand on busy world highways, as Guy Woodford reports Small footprint; minimum disruption after impact; lower labour costs; all said to be elements contributing to the growing popularity of the Trend terminal from Trinity Highway Products. This family of end terminals offers a range of safe and efficient solutions to barrier ends with quick and easy assembly and installation. Trinity claims th
  • Highway project in Texas required demolition equipment
    May 1, 2018
    A contractor in Texas has used equipment from Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S. This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, t
  • Key projects free up Auckland's congested motorway network
    June 14, 2012
    A number of key projects in Auckland, New Zealand will free-up the city’s congested motorway network - Mary Searle reports.Auckland is a sprawling city, home to 1.4 million people, one third of New Zealand’s total population. Until recently, greater Auckland comprised Auckland city, North Shore city over the harbour bridge to the north, Waitakere city to the west and Manukau city to the south. An amalgamation of these various cities’ councils, plus the regional council and three district councils into one,
  • Safety measures aid workzone accident reduction
    February 20, 2012
    Everyone connected with the highway industry is involved in the efforts to cut down the number of work zone accidents. Patrick Smith reports. A few months ago, as road work resumed on America's highways and bridges, US Transportation Secretary Ray LaHood called on drivers to use extra caution in work zones. At the same time he commended the success in reducing overall roadway fatalities in each of the last seven years.