Moveable barrier cuts costs, aids motorists

Work on an award-winning US bridge was completed with savings and benefits to motorists through the help of an innovative barrier. The bridge replacement of US 31 over I-465 and Lick Creek in southern Indianapolis, state capital of Indiana, won the 2011 Honor Award from the American Council of Engineering Companies of Indiana. Stephen J. Christian & Associates of Indianapolis completed the design in less than nine months to allow Indiana Department of Transportation (INDOT) to take advantage of the favourab
February 20, 2012 Read time: 3 mins
The QuickChange Moveable Barrier from Barrier Systems

Work on an award-winning US bridge was completed with savings and benefits to motorists through the help of an innovative barrier.

The bridge replacement of US 31 over I-465 and Lick Creek in southern Indianapolis, state capital of Indiana, won the 2011 Honor Award from the 2853 American Council of Engineering Companies of Indiana.

Stephen J. Christian & Associates of Indianapolis completed the design in less than nine months to allow 2855 Indiana Department of Transportation (INDOT) to take advantage of the favourable bid conditions.

The work, completed late last year, called for replacement of the superstructure for the existing seven-span bridge. A new steel beam superstructure was selected in order to minimise the dead loads and utilise the existing substructure units.

US 31 is a busy urban arterial that carries over 54,000 vehicles per day, and it was apparent that the construction project would significantly impact traffic and cause major delays.

Lick Creek Bridge carries six lanes of traffic, with two through lanes in each direction and a ramp lane in both the northbound and southbound direction.

It was determined that the bridge was too narrow to maintain the current traffic flow during construction, and the original construction plans called for a temporary widening of the bridge that inflated the cost of construction to an estimated US$6 million.

Because US 31 has a directional traffic flow with a significantly higher volume in the northbound lanes during the morning peak and higher southbound volume in the evening peak, the concept of a moveable barrier was introduced.

The QuickChange Moveable Barrier (QMB) from 165 Barrier Systems, would physically separate the northbound and southbound traffic, but it could be quickly reconfigured several times per day to provide two lanes for peak traffic in each direction using a total of only three lanes in a 2/1, 2/2 configuration.

Because the bridge no longer had to be widened, the estimated project cost was revised to $4.8 million, a saving of $1.2 million over the original estimate.

"In addition to the cost savings, the moveable barrier provided benefits to motorists by maintaining the same number of traffic lanes throughout the entire project, and the surrounding neighborhoods benefited from the reduced impact to air quality that is typically created from traffic backups," says Barrier Systems.

"The project exceeded INDOT's original expectations in several categories including overall project cost and potential impact on the motoring public."

Related Content

  • Golden Gate Bridge gets Lindsay Transportation Solutions barrier
    March 10, 2015
    The iconic Golden Gate Bridge in California is now benefiting from the introduction of a new moveable barrier. Supplied by US specialist Lindsay Transportation Solutions, formerly Barrier Systems, and a division of Lindsay Corporation, this purpose-built moveable central divider will help maximise capacity while simultaneously boosting safety on the landmark structure. Constructed in the 1930s and first opened to traffic in 1937, the Golden Gate has coped extremely well with the years. Soundly engineered,
  • Reducing congestion while maximising safety in road construction work zones
    April 30, 2015
    Mike Dreznes, executive vice president at the International Road Federation (IRF) discusses road safety for work zone areas. Work zones around the world can create significant congestion and can cost society billions of dollars. Estimates in the United States alone include approximately 87,600 work zone crashes involving 37,500 injuries that result in 482 million lost hours, valued at approximately US$6.5 billion. When considering these numbers worldwide, it becomes clear that work zone safety and work zone
  • More on the Newmarket Viaduct replacement
    June 15, 2012
    When it was completed in 1965 – just six years after the Auckland Harbour Bridge – the six-lane Newmarket Viaduct with its tall, slender piers was something of an engineering wonder, the first of its kind in the Southern Hemisphere. Forty years on it had become a much-maligned contributor to Auckland’s chronic traffic congestion, too weak seismically to withstand the heaviest loaded trucks let alone a severe earthquake, so narrow in the shoulders that any accident stopped traffic flow and made it difficult
  • US city of Vancouver approves new I-5 bridge
    July 18, 2022
    Vancouver in the US state of Washington and Portland in the state of Oregon are aiming for a new road bridge with the possibility of accommodating light rail transport.