India road delivery delays for major projects

India’s road network development programme is facing a series of delays with several major projects now well behind schedule.
June 19, 2017 Read time: 1 min

India’s road network development programme is facing a series of delays with several major projects now well behind schedule. In all 22 road projects stretching some 1,239km and worth a total of US$2.84 billion. The contracts for the 22 projects were awarded from July 2016 to October 2016 but construction work is yet to commence.

For most of the projects, the delays are due to hold-ups in obtaining the necessary environmental permits, securing financing and finalising the acquisition of the land on which the various routes will be built.

Related Content

  • Indian expressway concession agreed
    January 24, 2022
    A key expressway concession is agreed for Uttar Pradesh in India.
  • Volvo moves mountains in Portugal
    June 8, 2015
    Volvo Construction Equipment is opening up the remote Portuguese regions of Duoro and Trás-os-Montes for development through one of the largest road tunnels in the Iberian Penninsula. The Túnel do Marão project takes in Portugal’s sixth largest mountain, the Serra do Marão. At a height of 1,415m above sea level, it presents a major obstacle between the country’s second city Porto, located on the coast, and Vila Real near the Spanish border, even since the construction of the winding IP4 highway, built in t
  • The UK’s first PFI road project opens
    May 18, 2012
    A new bypass around Carlisle in North West England has opened to the public two months ahead of schedule. The Carlisle Northern Development Route (CNDR) starts from the Wigton Road (A595) to the south west of Carlisle, follows a route around the west of the city crossing the River Eden on a new bridge near Stainton and the West Coast Main Line on a new two-lane bridge constructed at Kingmoor. The road layout allows easier access to West Cumbria from the roundabout at Junction 44 of the M6 rather than havin
  • Administrative delay for Slovakia bypass
    March 11, 2016
    An administrative delay has been holding up the commencement of the new bypass project around Slovakia’s capital, Bratislava. The project is being handled by a joint venture team headed by Spanish contractor Cintra Infraestructuras. The project’s agreement should have been signed on 4th March 2016 by the Slovakian Government. A reason for the delay has not been revealed. The ring-road project is worth some €1.9 billion and will be constructed under the public-private partnership (PPP) model.