Bechtel achieves tricky bridge replacement in tight timeframe

Contractor Bechtel has worked with Network Rail to complete a major road bridge upgrade in the UK. A construction team worked 104 hours consecutively to replace the bridge, located at Reading Station.
March 21, 2012 Read time: 3 mins
Contractor 4138 Bechtel has worked with 4139 Network Rail to complete a major road bridge upgrade in the UK. A construction team worked 104 hours consecutively to replace the bridge, located at Reading Station.

The work forms part of the Reading Station Area Redevelopment project in England and involved installing a new bridge at Cow Lane.

The project was carried out within a tight time frame of 104 hours while the Reading West Curve rail line was taken out of commission for the work. The task of replacing Cow Lane Bridge started at 5pm on December 24th, when the rail freight line above was closed so that demolition of the old 6m span bridge could take place.

In the evening of December 26th, a self-propelled modular transporter lifted the new 14m span, reinforced concrete bridge into place. This led to the on time hand back to operations of the Reading Western Curve.

The bridge move was similar to the Caversham Bridge deck lift delivered by Bechtel, Network Rail, and contractors in 2010. However, in this case, the task was even more complex as instead of the new bridge being moved on site in pieces, here the deck, abutment, wing walls and anchor blocks were lifted as a single, complete 1,600tonne unit. More than 270 people worked around the clock to complete the work on time and to ensure that on 27th December, trains could run as scheduled. “As we were moving a whole bridge into place there was no margin for error. This was a complex task and the results are testimony to what can be achieved through collaboration in the rail industry and with its partners,” said Wayne Chin, implementation director, Bechtel. The bridge replacement is part of Network Rail’s £850 million improvement programme for Reading station and the surrounding area.

Cow Lane Bridge was a notorious bottleneck in the Reading area but the new bridge can accommodate two lanes of traffic including double decker buses, a cycle path and pavement which will help to reduce congestion. "The Cow Lane works went very well indeed. The team overcame some significant problems. When the old Cow Lane bridge was removed, the ground was found to be much more waterlogged than had been expected, and we had to spend around seven hours in extra preparation before we could start to move the new bridge. Despite this, we caught up the time and handed back the possession with four minutes to spare, which is a testament to the resourcefulness and determination of the team”, said Robbie Burns, delivery director for Wales and West, Network Rail.

Additionally, during this time the Reading Station Area Redevelopment project successfully delivered substantial station works including commissioning of the southern lines new platform 4 complete with new track and signalling system, widening of existing Platform 10 and the station platform renumbering.

For more information on companies in this article

Related Content

  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.
  • Cleveland Bridge is all decked out on the England’s A14 scheme
    June 4, 2019
    As part of Highways England’s A14 upgrade project from Cambridge to Huntington, Cleveland Bridge installed two 1,050tonne pre-assembled bridge decks in just 11 hours. Months of detailed planning and client liaison ensured the 47.5m-long bridge decks, each containing 330tonnes of steel and 720tonnes of concrete, were successfully travelled to the site and lowered onto the abutments. On-site civil engineering works were undertaken by the A14 Integrated Delivery Team, a joint venture between Costain,
  • Duisburg double for lift specialist Sarens
    June 5, 2024
    Heavy lift specialist Sarens overcame challenging wind and water conditions during installation of two strategic road bridges - the Oberbürgermeister Karl Lehr Brücke and the Hafenkanalbrücke - in the German city of Duisburg.
  • Romania’s important bridge project
    October 5, 2022
    Romania’s important Braila Bridge project will deliver a key crossing spanning the Danube River