Skip to main content

Terex Superlift 3800 crawler crane lifts Schoneck Bridge into place

The new 15m-long, 66tonne Schöneck bridge was recently installed in Germany’s Saarland municipality of Kirkel. Trier-based Steil Kranarbeiten used its Terex Superlift 3800 lattice boom crawler crane to complete the project. Two months before, the old 1960s bridge, not then in use, was cut into eight sections and lifted out using a Terex AC 350/6 all-terrain crane. “Since both the old and the new bridges cross over the Intercity-Express Paris-Mannheim electric train route, overhead lines had to be disconn
January 4, 2016 Read time: 2 mins
Terex crane helps lift in new bridge in Germany
The new 15m-long, 66tonne Schöneck bridge was recently installed in Germany’s Saarland municipality of Kirkel. Trier-based Steil Kranarbeiten used its 1222 Terex Superlift 3800 lattice boom crawler crane to complete the project.

Two months before, the old 1960s bridge, not then in use, was cut into eight sections and lifted out using a Terex AC 350/6 all-terrain crane. “Since both the old and the new bridges cross over the Intercity-Express Paris-Mannheim electric train route, overhead lines had to be disconnected before the lifts were done. To avoid disruption to the train service, we had a window of only a few hours in both cases,” said Martin Mittler, one of the Steil managers for the project.

The work site was also in a residential area, a tight space for the 19 trucks delivering the Superlift 3800 crane’s components on site and setting it up with the Terex assist crane.

“The modular quick-connect system makes it possible to split the crane’s basic structure into two parts, one reason why the Superlift was chosen,” said Mittler. It was set up in two days in an LH1 configuration with a 42m main boom, 205tonnes of superstructure counterweight and 50tonnes of central ballast. The unstable working area for the crane had to be prepared with red ironwood crane mats to bear the machine’s weight.

The bridge structure was delivered in two sections and welded on-site, weighing in total 70tonnes, including slinging gear. After the load was meticulously rigged for balance, power to the overhead lines was turned off and the lift started.

The operator lifted the bridge, which was rigged at four attachment points, to a height of 6m at a working radius of 26m, in order to swing it over the tracks.

The working radius was increased to around 30m by lowering the boom and moving it forward with the Superlift by about 1m. The bridge was set down on supports with laser-like precision.

The tail end of the lift also went smoothly. Then, in just ten hours, the Superlift 3800 was disassembled and ready to truck to its next job.

For more information on companies in this article

Related Content

  • Crane lifts in bridge structure in Germany
    December 14, 2015
    A Terex crawler crane has been used to lift out a concrete bridge in the German town of Zweibrücken. The work was carried out shortly after the Terex Superlift 3800 lattice boom crawler crane had been supplied to Trier-based specialist Steil. The crane hire firm already had four Terex crawler cranes in its fleet with this new arrival bringing the number to five. The machine had a particularly short journey to make to the job site as it had just been manufacturerd at the Terex facility located in Zweibrü
  • Crane versatility helps with bridge building
    August 14, 2014
    The versatility and mobility of a Terex crawler crane has helped enormously with the construction of a new road bridge in Luxemburg. The Terex Superlift 3800 lattice boom crawler crane owned by Trier-based Steil Kranarbeiten was used to build a bridge in Luxemburg only two days after the same machine was used on a job in the Hunsrück mountain range. The machine was needed to lift a 440m long bridge across a valley, connecting a new section of highway.
  • Terex Superlift 3800 crane rises to the challenge in Alsace
    May 14, 2015
    Crane service provider Sarens has used a Terex Superlift 3800 lattice boom crawler crane to lift a pedestrian and bicycle steel bridge over the A4 Autoroute near Schiltigheim, in the Aisace region of France. The job was out of the ordinary, according to the Sarens Group, a transport and specialised rigging specialist based in Wolvertem, Belgium. “We didn’t have a special permit for a heavy-load transport with the required weight,” said Sarens project manager Joost Elsen.
  • Super job for a Demag CC 3800-1 without a Superlift counterweight
    July 4, 2019
    A Demag CC 3800-1 crane with an 84m-long main boom was recently set up in Germany without a Superlift counterweight to save space. The jobsite was the replacement of the old viaduct on the A45 Freeway that spans the Lahn River near Dorlar in Germany. Bietigheim-Bissingen-based crane service provider Wiesbauer solved the site’s space issues by using a Demag CC 3800-1. “This site required us to lift loads of 96-148tonnes at radii of 40-64m, so there was no option but to use a crawler crane in the 650tonne c