Terex Superlift 3800 crawler crane lifts Schoneck Bridge into place

The new 15m-long, 66tonne Schöneck bridge was recently installed in Germany’s Saarland municipality of Kirkel. Trier-based Steil Kranarbeiten used its Terex Superlift 3800 lattice boom crawler crane to complete the project. Two months before, the old 1960s bridge, not then in use, was cut into eight sections and lifted out using a Terex AC 350/6 all-terrain crane. “Since both the old and the new bridges cross over the Intercity-Express Paris-Mannheim electric train route, overhead lines had to be disconn
January 4, 2016 Read time: 2 mins
Terex crane helps lift in new bridge in Germany
The new 15m-long, 66tonne Schöneck bridge was recently installed in Germany’s Saarland municipality of Kirkel. Trier-based Steil Kranarbeiten used its 1222 Terex Superlift 3800 lattice boom crawler crane to complete the project.

Two months before, the old 1960s bridge, not then in use, was cut into eight sections and lifted out using a Terex AC 350/6 all-terrain crane. “Since both the old and the new bridges cross over the Intercity-Express Paris-Mannheim electric train route, overhead lines had to be disconnected before the lifts were done. To avoid disruption to the train service, we had a window of only a few hours in both cases,” said Martin Mittler, one of the Steil managers for the project.

The work site was also in a residential area, a tight space for the 19 trucks delivering the Superlift 3800 crane’s components on site and setting it up with the Terex assist crane.

“The modular quick-connect system makes it possible to split the crane’s basic structure into two parts, one reason why the Superlift was chosen,” said Mittler. It was set up in two days in an LH1 configuration with a 42m main boom, 205tonnes of superstructure counterweight and 50tonnes of central ballast. The unstable working area for the crane had to be prepared with red ironwood crane mats to bear the machine’s weight.

The bridge structure was delivered in two sections and welded on-site, weighing in total 70tonnes, including slinging gear. After the load was meticulously rigged for balance, power to the overhead lines was turned off and the lift started.

The operator lifted the bridge, which was rigged at four attachment points, to a height of 6m at a working radius of 26m, in order to swing it over the tracks.

The working radius was increased to around 30m by lowering the boom and moving it forward with the Superlift by about 1m. The bridge was set down on supports with laser-like precision.

The tail end of the lift also went smoothly. Then, in just ten hours, the Superlift 3800 was disassembled and ready to truck to its next job.

For more information on companies in this article

Related Content

  • Heavy lifting
    January 7, 2019
    UAE-based crane service provider Al Faris dispatched a team to Hamriyah, to lift three 72m-long, 130tonne spud legs from a barge. The job needed a powerful and precise crane and a Demag CC 3800-1 proved to be a highly suitable machine for the project. The unit first had to be transported to the worksite. The company’s own lowbed trailers needed a good ten hours to complete the 82km journey from the Al Faris location in Dubai Industrial City to the worksite. Al Faris’ own all-terrain cranes were used in ord
  • Giving credence for Clearwater revival
    October 29, 2018
    The Minnesota Highway 24 Bridge spanning the Mississippi River at Clearwater is not a major structure. However, it does play a key role as the 376.4m-long bridge links US Highway 10 and Interstate 94. These routes run parallel on opposite sides of the Mississippi River and connect St Cloud to Minneapolis. There was a need to replace the old bridge, built in the 1950s, as it has been designated functionally obsolete, while it featured a restricted maximum load of 36.3tonnes. The price tag to demolish and
  • Terex launches Superlift 3800 crawler crane
    January 6, 2017
    Terex Cranes has replaced its CC2800-1 crawler crane with the Superlift 3800 lattice boom, offering improved speed and efficiency for customers. The 3800 can handle loads of up to 650tonnes at a radius of 5-12m and has a maximum load moment of 8,426t/m. Terex says that customers have been involved in the new crane’s development from the start, resulting in improvements in many areas. The crane uses the Terex Crane Fall Protection System, with additional railings installed around the superstructure. It is th
  • Terex launches Superlift 3800 crawler crane
    April 18, 2013
    Terex Cranes has replaced its CC2800-1 crawler crane with the Superlift 3800 lattice boom, offering improved speed and efficiency for customers. The 3800 can handle loads of up to 650tonnes at a radius of 5-12m and has a maximum load moment of 8,426t/m. Terex says that customers have been involved in the new crane’s development from the start, resulting in improvements in many areas. The crane uses the Terex Crane Fall Protection System, with additional railings installed around the superstructure. It is th