Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Presidio Parkway: the Golden Gate Bridge’s new southern approach road
    May 29, 2013
    Work on the Presidio Parkway, a new breathtaking and eco-friendly southern approach road to San Francisco’s Golden Gate Bridge, has entered its crucial second and final phase. As Guy Woodford reports, the vital US$1 billion project has overcome legal as well as environmental challenges to stay on course for its expected 2016 completion Just after 9pm on Friday April 27, 2012 a large public crowd looked on excitedly as a fleet of more than 40 R&L Brosamer and Ferma Corporation deployed hydraulic demolition h
  • Mini-bridge aids Forth repairs
    July 17, 2012
    An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
  • RMD formwork for Qatar’s tallest bridge on Doha East Corridor
    July 6, 2016
    RMD Kwikform will be supplying tens of thousands of tonnes of its formwork and shoring for construction of Qatar’s tallest bridge on the Doha East Corridor project As well as the bridge, the Corridor contract comprises four interchanges at a total cost of US$612.5 million. Ashghal, Qatar's Public Works Authority, awarded the Corridor project to China Harbour Engineering Design and Construction. Built as a five-lane 11km bypass in Doha, the capital of Qatar, the project will also cater for a rail line
  • Tees Valley crossing project consultation nears an end
    May 9, 2019
    Public consultation is nearly closed for a possible new crossing across the River Tees in northern England that could cost upwards of €350 million. A €230-290 million Tees Viaduct Capacity Enhancement project is the preferred option against a €350 million Tees Viaduct option, according to the recently created Tees Valley Combined Authority, the local government. Capacity Enhancement project would see a two-lane bridge built parallel to the existing A19 viaduct to carry traffic travelling northbound an