Peri has Polish bridge covered

A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
February 6, 2012 Read time: 3 mins
A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used.

Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.

The individual sections of the superstructure are concreted directly together here and connected by means of tensioning cables. Subsequently, the hardened bridge section is raised a few millimetres and moved forward together with the other finished segments by one cycle length in the direction of the bridge's longitudinal axis.

Prefabrication of the individual repetitive bridge sections is being carried out with a stationary formwork, and a temporary protection roof, based on the 298 PERI UP modular scaffold, spans the working area and allows weather-independent construction of the individual sections for the superstructure.

According to the German formwork manufacturer this is one of the factors that allowed the 2296 Skanska-1547 NDI Joint Venture to reduce the construction period by three months.

For concreting work on the hollow box profile, a construction time of a year was originally planned, and as work started in November 2009, minimum temperatures of up to -25°C were expected during the winter.

To cater for the weather, the contractor planned the temporary protection roof for the construction phase: the possibility of renting the LGS (lattice girder system) protection roof for the period of use provided an economical solution.

Altogether, the jobsite team is using four roof structures: two smaller, permanently installed tents are used for reinforcement work preparations, while two movable protection roofs on basis of the LGS span the formwork and concreting areas.

To ensure unhindered material and concrete installation, the design allows the protection roofs to be moved. The girder supports are equipped with 55.5m long rails, which are over twice as long as the protection roofs and which are easily moved by two to four people. The wheel allows the roofs to be moved in a longitudinal direction.

"At the level of the girder, the static system of a single-span beam with one stationary and one movable support can be realised without any problems by means of system components," says PERI.

The spatial arrangement of the two sets of incremental launching equipment gave the position for the weather protection roofs: the available space between the formwork for both lanes was very limited. Load transfer of the support construction of both weather protection roofs had to be guaranteed via a common central support.

"With Keder track and sheeting, the scaffold constructions result in very light and translucent roofs. The solution in Grudzi?dz also includes a side and gable covering. "Overlapping of the sheeting at all joints ensures a tightly-fitting enclosure which at the same time can easily be opened. With extremely low outside temperatures, the temporary tents were also heated.

"An additional positive effect of the enclosure is the consistently high concrete quality achieved throughout due to the constantly good setting process."

For more information on companies in this article

Related Content

  • Doka and MFE in Malaysia join forces
    March 11, 2024
    Doka's purchase of MFE Formwork Technology, based in Kuala Lumpur, comes after its acquisition early last year of US-based scaffolding manufacturer and rental business AT-PAC.
  • All aboard the Wirtgen paving train on Germany’s A7 project
    February 21, 2019
    The A7 is being widened between Hamburg and Bordesholm from four lanes to six - in some places to eight - to ensure the motorway remains an efficient traffic artery. The aim is to create a pavement with a high degree of driving comfort but which withstands the loads of heavy-goods traffic. For widening the 60km stretch in the Schleswig-Holstein region, consortium Via Solutions Nord and joint venture ARGE A7 Hamburg-Bordesholm opted for steel reinforced concrete paving with an exposed aggregate concrete s
  • Mersey Gateway Project reaches half-way point across the Mersey
    March 10, 2017
    The Mersey Gateway project in England has passed a significant milestone, with over half of the main bridge deck stretching across the River Mersey. Work to install stay cables on the main bridge also passed a key point, with installation of the 31st 150m long cable – the halfway point for stay cable installations on the pylon. When complete, 146 stay cables will support the 1km-long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000tonnes. “We’re now more than 50
  • Clever approach to reducing bridge vibrations
    November 14, 2013
    Reducing vibrations on a bridge, supplying high-quality binders to emerging countries and helping small and medium players with warm mix, this month’s stories showcase some innovative bitumen technology solutions - Kristina Smith reports The Kessock Bridge in the Highlands of Scotland has become the third bridge in the UK to be resurfaced with Gussasphalt. A dense mastic asphalt containing Nynas Endura N5, a polymer modified binder, Gussasphalt has been designed to have a longer life than standard mastic as