Modular water treatment solutions

Siltbuster has provided Costain with four modular treatment solutions, to be used during the delivery of the £200 million Preston Western Distributor Road, linking Preston and southern Fylde to the M55 motorway.
May 3, 2021 Read time: 2 mins
A modular system from Siltbuster is being used to protect water courses around the Preston Western Distributor Road project

The 4km dual carriageway is set to open in 2023 and includes a new motorway junction, four new bridges and three underpasses. The route goes past several surface watercourses, including the Savick Brook and the Lancaster Canal. With this in mind, Costain contacted Siltbuster and tasked it with planning the water runoff management.

Siltbuster has deployed four water treatment systems to cover the multiple controlled watercourses where water is being released from the site. Each location is regulated by the Environment Agency, with the Environmental Permit requiring total suspended solids to be less than 100mg/litre and a pH value between pH6 and pH9 to be achieved consistently.

In order to protect the north-west's aquatic ecosystems and habitats, each Siltbuster unit needed to be capable of treating flows of up to 40m3/hr. To deliver this, all of the systems include two-stage flow proportional chemical dosing of coagulant and flocculant to improve the settlement rates of the very fine suspended clay solids, and an 8m3 tank complete with mixers and a HB50 lamella clarifier. The modular nature of these solutions means additional capacity can easily be added should there be greater volumes of water needing to be treated.

Costain said that Siltbuster systems have helped keep the project on track by ensuring the contractor is in line with its environmental permit at all times, protecting the surrounding habitats. Because Siltbuster was consulted from an early stage in the project, the firm was able to advise on temporary flexible modular solutions that could be rapidly deployed from its hire fleet as soon as the need arose. The company has also offered Costain specialist technical advice and training, helping to protect the aquatic ecosystems around the project.

For more information on companies in this article

Related Content

  • R&W takes in-house the recycling of dry and wet waste
    January 15, 2016
    With the introduction of EU regulations in 2012 controlling the disposal of dry and wet waste from road sweepings and gully waste and it is not acceptable to send this material to landfill. Many local authorities have had to find an alternative solution. R&W Civil Engineering in the southern UK country of Hampshire, is a specialist in highway construction, maintenance and other transport related services. It, along with other contractors started transporting waste material to the nearest processing stati
  • Tyne tunnel's water quality checks
    February 6, 2012
    Five buoy-mounted automatic water quality monitors (AWQMs) have been installed by YSI Hydrodata engineers at the new Tyne Tunnel project in north-east England. The equipment on the second vehicle tunnel under the River Tyne, currently one of the UK's largest construction projects, aims to ensure that construction operations do not significantly affect river water quality. Unusually, the contractors have not taken ownership of the instrumentation, preferring instead to simply purchase the data and alarms. Th
  • Geosynthetics stabilise differential settlement
    May 3, 2012
    The ongoing Highways Agency A66 Carkin Moor to Scotch Corner project involves upgrading the original single carriageway to address safety concerns, particularly at junctions and crossings. Where differential settlement is threatening a remodelled junction, Tensar International's new TriAx geogrid provides an additional dimension of stability, saving design and build contractors Balfour Beatty Regional Civil Engineering Limited (BBRCEL) the heavy time and costs inherent in conventional remedial solutions and
  • Geosynthetics stabilise differential settlement
    March 14, 2012
    The ongoing Highways Agency A66 Carkin Moor to Scotch Corner project involves upgrading the original single carriageway to address safety concerns, particularly at junctions and crossings. Where differential settlement is threatening a remodelled junction, Tensar International's new TriAx geogrid provides an additional dimension of stability, saving design and build contractors Balfour Beatty Regional Civil Engineering Limited (BBRCEL) the heavy time and costs inherent in conventional remedial solutions and