Mobile grouting trailers for soil nail rigs

Geotechnical specialists, Bachy Soletanche and Carillion Piling are currently working on an £18 million (e21 million) geotechnical contract as part of carriageway improvements on the M1 motorway to the north of London, England. The work between junctions 10-13, Luton to Milton Keynes, is being carried out for the Costain Carillion joint venture working on behalf of the Highways Agency. The piling and soil nailing works are to facilitate the conversion of the current hard shoulder to a peak-time running lane
February 7, 2012 Read time: 3 mins
Geotechnical specialists, 1485 Bachy Soletanche and 2354 Carillion Piling are currently working on an £18 million (e21 million) geotechnical contract as part of carriageway improvements on the M1 motorway to the north of London, England.

The work between junctions 10-13, Luton to Milton Keynes, is being carried out for the Costain Carillion joint venture working on behalf of the Highways Agency.

The piling and soil nailing works are to facilitate the conversion of the current hard shoulder to a peak-time running lane with further junction improvements including 60 improved sign gantries and emergency refuges, over the 25km length.

Designed by the 2309 Highways Agency's engineer, Parsons Brinkerhoff, and Costain Carillion's engineer, Scott Wilson, there has been no need for additional land take.

The work is phased between the three junctions on only one carriageway at a time to avoid disruption to the travelling public and to abide by health and safety regulations.

Due to last up to 90 weeks, the project includes 250 Continuous Flight Auger (CFA) gantry piles each 750mm diameter and up to 20m long, with vibrated full-length reinforcement cages, 1600, 750mm diameter CFA piles for the contiguous bored pile walls up to 11m long in the emergency refuges, and 22,000 hollow stem and solid bar soil nails to stabilise the new cuttings and embankments, which are between 5m and 12m long.

The embankments are made up of a variety of fill materials, and the cutting slopes are generally within clay with flints over chalk (these achieve a maximum thickness of 5m and are thought to have originated from prolonged in situ weathering of outcrops of the Woolwich and Reading beds, while the chalk formation occurs as upper chalk, middle chalk, grey chalk and chalk marl along the length of the route).

The piling jv team said of the works: "High levels of safety have been paramount with this project due to working close to live traffic and some overhead power lines. This has led to a number of innovations by the Bachy Soletanche and Carillion Piling jv, including guarded soil nail rigs with a safe operator platform, improved guarding and auger cleaning for CFA piling, rope access systems, mobile grouting trailers, and a new Geoweb securing system. The new developments ensure work can be completed within the specified time frame with minimised safety risks."

For more information on companies in this article

Related Content

  • Green running for Soilmec’s Blue Tech SR-75
    June 26, 2020
    More power but less fuel consumption is a key environmental feature of Soilmec’s SR-75 piling rig, the latest addition to the company’s Blue Tech line. Alongside increased transportability, the SR-75 decreases fuel consumption with its Tier 4 final engine to provide cutting-edge rig control and remote monitoring with DMS (distributed monitoring system).
  • Improving a key route through Florida
    November 9, 2015
    Upgrading a key route through Florida – novel construction techniques are helping widen a road in difficult geological conditions – Lucio Garofalo reports. A major road widening project underway in Florida is due for completion soon. The work will improve an important section of road, reducing congestion at peak period and cutting travel times for drivers. The US 331/SR83 highway runs for some 79km and provides an important link in Florida’s Panhandle area, as it connects with Route 98.
  • BAUER mobilises rigs for UK’s A19/A1058 coast road piling works
    April 10, 2017
    In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange. The Sisk Lagan joint venture, the main contractor, called upon Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in
  • Kuwait’s key causeway contract under construction
    July 4, 2016
    A new causeway, crossing the Bay of Kuwait, is under construction and providing a major engineering challenge - Mike Woof reports. The new Sheikh Jaber Al-Ahmad Al-Sabah Causeway Project being built across the Bay of Kuwait is a massive engineering project that is costing around US$3 billion in all. This highly complex project involves the design, build, completion and maintenance of the causeway, which spans Kuwait Bay between Kuwait City and the Subiyah area. The 36km Sheikh Jaber Al-Ahmad Al-Sabah Cau