BAUER mobilises rigs for UK’s A19/A1058 coast road piling works

In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange. The Sisk Lagan joint venture, the main contractor, called upon Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in
April 10, 2017 Read time: 2 mins
Bauer Technologies is installing 583 contiguous rotary bored piles with diameters ranging from 600-1500mm.
In north-east England, work is underway to create an improved A19/A1058 Coast Road junction. The £75m scheme in the city of Newcastle involves the upgrade of a roundabout to an ambitious three-level interchange.

The Sisk 2340 Lagan joint venture, the main contractor, called upon 8350 Bauer Technologies, to complete the piling works for critical structures. Bauer’s parent company, Bauer Spezialtiefbau, is a global construction company specialising in complex and specialist foundation works, with its head office in Schrobenhausen, Germany.

Bauer’s scope of works is to install 583 contiguous rotary bored piles with diameters ranging from 600-1500mm. The piles, up to 31m long, are founded in sandstone bedrock to form contiguous pile walls, creating the trough for the future A19 “dive-under”. A number of the retaining wall piles also act as hybrid design elements by carrying the load of three major single-span bridges across the underpass. In order to verify the capacity of these critical foundations, Bauer will carry out three permanent pile load tests using the innovative Osterberg method.

The project is particularly challenging because it entails working within a major roundabout with a heavy volume of traffic, according to Martin Blower, managing director of Bauer Technologies.

In order to manage associated risks efficiently, Bauer is working closely with the joint venture and 8100 Highways England – the government agency - to implement stringent health and safety processes. In addition, Bauer said that it is “enthusiastically participating” in Highways England’s “Raising the Bar” scheme designed to raise standards in working efficiencies and quality of workmanship, as well as health and safety.

Piling works started in December 2016, with mobilisation of a Bauer BG30 rig, which will be followed by a second machine in early 2017. Piling works will be carried out in two phases and are expected to be complete by the end of this year.

For more information on companies in this article

Related Content

  • North East UK’s A19 /A1058 Coast Road triple-deck junction opens
    April 5, 2019
    More than 80,000 drivers a day are now using the recently opened and - first ever - North Tyneside triple-deck highway junction in the northeast. England’s A19 /A1058 Coast Road junction improvement scheme, being done for the client Highways England, was opened on time. However, there will be some overnight closures in the next several weeks to complete the landscaping, traffic light and footpath work. A time capsule has been buried on site and is due to be opened in 2118. Work started in June 2016 on
  • Work to start on triple-deck roundabout in North Tyneside, UK
    June 30, 2016
    Construction of a major triple-deck roundabout in North Tyneside, England starts in August.

    The roundabout is part of an upgrade to the A19/A1058 Coast Road junction that includes lowering the A19 beneath the existing A1058 Coast Road and roundabout.

    The €90 million scheme is on the main route to and from the Tyne Tunnel and will mean that people travelling along the A19 will no longer have to queue at the roundabout to go continue their journey straight ahead. Instead, drivers will use a new section of road which will run under the junction.
  • Bauer’s BG 30, part of the rig manufacturer’s ValueLine platform
    March 7, 2016
    Bauer Maschinen is presenting a new generation of its ValueLine, a medium-sized platform range for bored piles with a diameter of up to 2.5m and a drilling depth of up to 70m. The platform range includes the BG 26 as the lowest priced-model and the larger version, the BG 30. The core element of the medium-sized platform range is the joint BT base carrier, which was entirely designed and constructed by Bauer. The modern and highly functional support does not just score points for its high safety standa
  • Bauer’s BG 30, part of the rig manufacturer’s ValueLine platform
    January 6, 2017
    Bauer Maschinen is presenting a new generation of its ValueLine, a medium-sized platform range for bored piles with a diameter of up to 2.5m and a drilling depth of up to 70m. The platform range includes the BG 26 as the lowest priced-model and the larger version, the BG 30. The core element of the medium-sized platform range is the joint BT base carrier, which was entirely designed and constructed by Bauer. The modern and highly functional support does not just score points for its high safety standa