Skip to main content

Highway project in Texas required demolition equipment

A contractor in Texas has used equipment from Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S. This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, t
May 1, 2018 Read time: 4 mins
The Brokk unit was able to work effectively for long shifts without tiring the operator
A contractor in Texas has used equipment from 7571 Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S.


This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, trucks entering were often forced to immediately cross all lanes of traffic to reach their exit. TxDOT officials decided to add a lane in each direction, expanding the road to eight lanes, as well as realigning ramps. In addition, the Department of Defense granted US$20 million for the construction of a direct connector for southbound I-35 to I-410 to reduce congestion for vehicles heading into a busy US Army hospital complex. Overall, the improvements would boost safety and capacity.

The department hired general contractor Lane Construction for the four-year $61.2 million project and work began in late 2013.

Several sections along the stretch required widening bridges, and one section involved filling a 5.9m gap between two parallel bridges. The section also called for a new auxiliary lane, so concrete rails and some of the bridge deck concrete needed to be removed. Lane Construction hired the local specialist demolition contractor JR RAMON for that portion of the project, as well as several other bridges.

Before connecting the bridges, the contractor would need to remove 914mm-tall, 305mm-thick, rebar-reinforced concrete rails and three stretches of 122m-long, 914mm-wide and 152mm-deep concrete bridge decks. Two of those stretches were on the inner sides of the bridges and one was on the southbound side’s outer section. Each stretch needed to be removed in just three days to minimise traffic impact. A further challenge was that the two layers of rebar needed to remain undamaged so Lane Construction could reuse it to tie into the new concrete decking.

JR RAMON’s demolition crew started with the outer section, using a 2300 Komatsu PC360 excavator with a 2294 CAT pulveriser attachment to reach up and demolish the barriers from the roadway below.

Next, the team removed a 122m section of concrete from the southbound bridge’s outer deck. JR RAMON used the excavator and pulveriser attachment to weaken the concrete up to the saw-cut concrete line on the first section before workers with hand tools removed the concrete.  The excavator was fast at removing the concrete but damaged the rebar in the process. TxDOT assessed the rebar and determined it would need to be replaced. The process to patch up the rebar was expensive and time-consuming, setting the project back several days and costing more than $100,000.


JR RAMON decided to bring in a Brokk machine for the job as it already owned an electric B160 model. The firm realised its electric-powered machine’s cables and generator would clutter the single lane of traffic. After realising the high costs of using an excavator for the work, the firm decided to purchase a diesel-driven Brokk 120D specifically for the inner sections.

Armed with this new tool, JR RAMON took on the inner sections of the two bridges. Crews again used the excavator to remove the concrete rails, but then moved in with the Brokk machine to demolish the bridge deck concrete. An operator used the B120D’s remote control to direct the powerful and precise three-part arm with an 161 Atlas Copco SB 152 breaker to remove the concrete while avoiding the underlying rebar.

In addition to leaving the rebar untouched, the Brokk machine increased productivity. The operator stood about 1.8m away, monitoring the work a safe distance from flying concrete as well as the 6.1m drop to the road below.

The B120D also saved the contractor considerable time when the team discovered the inner section cut line on the northbound bridge was off by 52mm.  Between the outer and inner sections, JR RAMON removed about 950tonnes of concrete.

After JR RAMON finished its portion, Lane Construction continued working on connecting the bridges as well as completing the other traffic improvements.

For more information on companies in this article

Related Content

  • Golden route to success
    July 20, 2012
    Built in 1937 and still the ninth longest suspension bridge in the world, the Golden Gate Bridge across San Francisco Bay remains in fine shape despite its age - Andrew Bardin Williams writes The Golden Gate Bridge turned 75 years old on May 27 and continues to play a key role in the transportation, engineering, construction and ITS communities. The structure has played an important historical role, an engineering success that boosted the economy of the region. And it also led the way as the first major pub
  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en
  • Kronprinsesse Marys Bro bridges Roskilde Fjord
    January 10, 2019
    A BESIX joint venture is giving the royal treatment to the new Kronprinsesse Marys Bro across Roskilde Fjord, writes David Arminas It was announced in September 2016 that Belgian group BESIX, in a joint venture (RBAI) with Italian firm Rizzani de Eccher and Spanish company Acciona Infraestructuras, had been chosen for the €133 million project. The award, by client Vejdirektoratet (Danish Road Directorate), marked the entry of BESIX into the Scandinavian market. Vejdirektoratet praised the winning bid as
  • Texas highway deal for joint venture
    August 12, 2021
    An important Texas highway project is being carried out by a joint venture.