Skip to main content

Highway project in Texas required demolition equipment

A contractor in Texas has used equipment from Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S. This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, t
May 1, 2018 Read time: 4 mins
The Brokk unit was able to work effectively for long shifts without tiring the operator
A contractor in Texas has used equipment from 7571 Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S.


This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, trucks entering were often forced to immediately cross all lanes of traffic to reach their exit. TxDOT officials decided to add a lane in each direction, expanding the road to eight lanes, as well as realigning ramps. In addition, the Department of Defense granted US$20 million for the construction of a direct connector for southbound I-35 to I-410 to reduce congestion for vehicles heading into a busy US Army hospital complex. Overall, the improvements would boost safety and capacity.

The department hired general contractor Lane Construction for the four-year $61.2 million project and work began in late 2013.

Several sections along the stretch required widening bridges, and one section involved filling a 5.9m gap between two parallel bridges. The section also called for a new auxiliary lane, so concrete rails and some of the bridge deck concrete needed to be removed. Lane Construction hired the local specialist demolition contractor JR RAMON for that portion of the project, as well as several other bridges.

Before connecting the bridges, the contractor would need to remove 914mm-tall, 305mm-thick, rebar-reinforced concrete rails and three stretches of 122m-long, 914mm-wide and 152mm-deep concrete bridge decks. Two of those stretches were on the inner sides of the bridges and one was on the southbound side’s outer section. Each stretch needed to be removed in just three days to minimise traffic impact. A further challenge was that the two layers of rebar needed to remain undamaged so Lane Construction could reuse it to tie into the new concrete decking.

JR RAMON’s demolition crew started with the outer section, using a 2300 Komatsu PC360 excavator with a 2294 CAT pulveriser attachment to reach up and demolish the barriers from the roadway below.

Next, the team removed a 122m section of concrete from the southbound bridge’s outer deck. JR RAMON used the excavator and pulveriser attachment to weaken the concrete up to the saw-cut concrete line on the first section before workers with hand tools removed the concrete.  The excavator was fast at removing the concrete but damaged the rebar in the process. TxDOT assessed the rebar and determined it would need to be replaced. The process to patch up the rebar was expensive and time-consuming, setting the project back several days and costing more than $100,000.


JR RAMON decided to bring in a Brokk machine for the job as it already owned an electric B160 model. The firm realised its electric-powered machine’s cables and generator would clutter the single lane of traffic. After realising the high costs of using an excavator for the work, the firm decided to purchase a diesel-driven Brokk 120D specifically for the inner sections.

Armed with this new tool, JR RAMON took on the inner sections of the two bridges. Crews again used the excavator to remove the concrete rails, but then moved in with the Brokk machine to demolish the bridge deck concrete. An operator used the B120D’s remote control to direct the powerful and precise three-part arm with an 161 Atlas Copco SB 152 breaker to remove the concrete while avoiding the underlying rebar.

In addition to leaving the rebar untouched, the Brokk machine increased productivity. The operator stood about 1.8m away, monitoring the work a safe distance from flying concrete as well as the 6.1m drop to the road below.

The B120D also saved the contractor considerable time when the team discovered the inner section cut line on the northbound bridge was off by 52mm.  Between the outer and inner sections, JR RAMON removed about 950tonnes of concrete.

After JR RAMON finished its portion, Lane Construction continued working on connecting the bridges as well as completing the other traffic improvements.

For more information on companies in this article

Related Content

  • Concrete paving key to Berlin's airport runways
    February 17, 2012
    High production concrete paving is proving a key feature at the new Berlin airport facility currently under construction The new Berlin-Brandenburg International Airport will soon provide improved links by air to the city. Work started in mid 2006 with the redevelopment of the existing Berlin Schönefeld Airport.
  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.
  • Tunnel project of Chilean capital Santiago
    April 8, 2015
    Tunnel construction in Chilean capital Santiago will help cut chronic congestion – Mauro Nogarin & Mike Woof write. Chile’s capital Santiago is a thriving city having benefited from the country’s economy growing strongly in recent years. The massive copper mining sector has helped boost the country’s GDP significantly in the past few decades, also aided by the growing international reputation of Chile’s large wine industry. The steady economic growth has resulted in an equally steady growth in average incom
  • Ground penetrating radar used to investigate tunnel deterioration
    May 13, 2015
    Using ground penetrating radar to determine reason for serious pavement settling in Kentucky-Tennessee tunnel Just a few years after the opening of the Cumberland Gap Tunnel, highway officials noticed moderate to severe settling of the continuously reinforced concrete pavement. The mountain tunnel provides an important link between Kentucky and Tennessee along US25E and the problem looked serious, with many voids discovered beneath the pavement surface. To investigate the problems, the Kentucky Transpor