Austria's first PPP project takes shape

North of the Austrian capital Vienna, one of the region's biggest transport infrastructure projects for decades is currently under construction, the A5 Nordautobahn. This will give the Greater Vienna region its first-ever high-capacity link to the Czech motorway and arterial road network, greatly easing congestion on the old main road. In the first phase of construction, 22.7km of motorway are to be built. Work on the second section, all the way through to the Czech border, is to start in 2010. The A5 Norda
July 31, 2012 Read time: 4 mins
The ALPINE site crew is using an adaptable construction made of Doka Top 50 large-area formwork and Staxo 100 load-bearing towers to form the carriageway slab, main beams and cantilever arms
North of the Austrian capital Vienna, one of the region's biggest transport infrastructure projects for decades is currently under construction, the A5 Nordautobahn.

This will give the Greater Vienna region its first-ever high-capacity link to the Czech motorway and arterial road network, greatly easing congestion on the old main road. In the first phase of construction, 22.7km of motorway are to be built. Work on the second section, all the way through to the Czech border, is to start in 2010.

The A5 Nordautobahn is the first Austrian roadbuilding project to be financed using the alternative financing technique of a public-private partnership (PPP). The Bonaventura consortium, made up of 981 Hochtief PPP Solutions, 1332 Alpine Bau and the French infrastructure specialists 2643 Egis, has a 30-year concession to finance, build and operate the Nordautobahn.

The works are being carried out by a joint venture of HOCHTIEF Construction and ALPINE Bau, and the total investment for the project is E933 million. The southern section of the Nordautobahn will be opened to traffic by 2010.

With 15 bridge structures, the 3.3km stretch of motorway between Gaweinstal and Schrick is technically the most challenging contract section of the route between the interchange at Eibesbrunn (also currently under construction) and the junction at Schrick. This section of motorway is projected to cost a total of around E225 million.

To build the technically demanding viaducts A5.11 and A5.12, the joint venture is relying on 203 Doka formwork technology.

The 154m long superstructures are all designed as identical, statically separated beam-and-slab constructions, and are each being executed in five casting steps using tableforms that have been specially adapted to the geometry of the structure.

"Fast, safe vertical access to the bridge superstructures, at a height of 14m off the ground, is provided by a Staxo stair tower," says Doka.

The twin superstructures of the two motorway bridges rest on two rows of piers, each consisting of five piers of up to 14m in height. These piers were 'climbed' using Doka wall formwork FF 20, in two casting steps.

In order to keep within the tight construction schedule, the 15m wide carriageway slabs and the massively dimensioned (2.4m high and 80cm wide) main beams are being cast in one single pour. For this application, Doka's formwork experts at its Vienna branch faced custom tables with Large-area formwork Top 50 and mounted them on heavy-duty Staxo 100 load-bearing towers. This construction includes a forming box for the space between the main beams.

"The formwork for the main beams is joined to the timber beam formwork for the carriageway slab, so it can be retracted in one piece with this when the time comes to strip the formwork. This helps us by giving us short stripping and repositioning times, and speedier forming operations overall", explains ALPINE supervisor Marcello Gebhardt.

The formwork elements for the 2.7m long cantilever arms are also joined to the formwork for the main beams, and so can be quickly pulled back from the concrete. The entire Doka formwork construction is mounted on field-built, site-provided falsework. Following completion of the first carriageway, this falsework is moved across on travelling units ready for use on the second superstructure, saving a great deal of time. To permit the custom tables to be repositioned by crane, site management, headed by Marcello Gebhardt, joined with Doka's Vienna branch to develop a modified crane fork that is perfectly tailored to the geometry of the custom tables.

After the final casting step, the formwork boxes and the cantilever arm formwork are moved out using a telescoping stacker truck and a specially designed fork. This innovative solution makes it possible to do without the gaps that would otherwise be needed in the carriageway slab for lifting out the formwork by crane. The forming operations are right on time and within budget, and are on track for completion by the end of this year.

For more information on companies in this article

Related Content

  • São Paulo's landmark bridge construction
    February 21, 2012
    To improve access from the east to São Paulo city centre, main contractor Construbase Engenharia is building a road complex comprising three viaducts and access ramps. The greatest challenge in Brazil's largest city is the showpiece Padre Adelino viaduct, a 122m long single-arch, single-span, cable-stayed concrete bridge moulded in situ with a parabola-shaped arch and a single-cell post-tensioned cantilever caisson
  • Meva’s Mammut 350 formwork makes the difference for Neckar viaduct
    April 19, 2018
    Formwork specialist Meva is helping replace the longest motorway bridge, the Neckar River viaduct in Germany’s south-west state Baden-Wuerttemberg Work on the 1.3km Neckar viaduct, part of the A6 motorway at Heilbronn, should be finished by 2022. It is part of the A6 expansion project between the Weinberger junction and Wiesloch/Rauenberg. The project is officially the new Neckar viaduct BAB 6 at Heilbronn. Federal Motorway 6, the A6, is also known as the BAB 6. The 477km motorway starts at the French b
  • Bridge uses new forming carriage
    February 7, 2012
    The Holzmatttal Bridge for the A98 autobahn in southern Germany stretches 410m across the valley, and on this build the newly-developed Doka forming carriage TU is said to have demonstrated precisely how it drives progress with extremely short cycle times and speedy forming and stripping out operations. The underslung carriage also permits unobstructed access for site traffic.
  • The bridge to reduced traffic
    February 28, 2012
    In Zaporozhye, the industrial metropolis in Ukraine's south-east, a multi-lane cable stayed bridge is being built alongside an older viaduct. On completion, this large-scale infrastructure project will massively reduce the traffic burden on the existing bridge and significantly improve the daily traffic situation at this major river crossing.