Amey chooses polystyrene blocks for Scottish tunnel infill

Amey recently completed an infill project to make safe a disused railway tunnel underneath the approach roads north of Scotland’s Forth Road Bridge. The 420m tunnel was part of the Dunfermline to North Queensferry railway line that provided a link to the ferry service until the opening of the Forth Bridge in 1890. The 4.3m-wide and 5.1m-high tunnel with vaulted roof and brick lining continued in use for freight until 1954. The tunnel runs underneath the A9000 and B981 on the northern approach to the Forth
June 25, 2018 Read time: 3 mins
Amey made light of the project by using expanded polystyrene (EPS) blocks
Amey recently completed an infill project to make safe a disused railway tunnel underneath the approach roads north of Scotland’s Forth Road Bridge.


The 420m tunnel was part of the Dunfermline to North Queensferry railway line that provided a link to the ferry service until the opening of the Forth Bridge in 1890. The 4.3m-wide and 5.1m-high tunnel with vaulted roof and brick lining continued in use for freight until 1954.

The tunnel runs underneath the A9000 and B981 on the northern approach to the Forth Road Bridge. Both tunnel ends had been sealed and the adjacent cuttings filled in, leaving a vertical shaft at each end as the only access points.

An 2958 Amey inspection had found parts of the tunnel degrading and in need of preventative maintenance to ensure continuing structural integrity. Due to the limited depth of cover above the tunnel, a failure could have had an impact on the roads overhead.

Two options were considered: an ongoing programme of inspection and maintenance or a one-off project to infill the tunnel with a low-cost material. The infill option was chosen because it would eliminate the need for future inspections or maintenance making it the more cost-effective solution in the long term.

After considering workforce safety, overall cost and the need to avoid disruption to the local community, it was decided to fill the tunnel with expanded polystyrene (EPS) blocks. These were manufactured to a specific compressive strength capable of resisting the weight of rock and tunnel lining in the event of a localised structural failure.

The EPS blocks were pre-cut to a size and weight to facilitate easy manual handling on-site. This allowed work to be carried out from the access shaft at the north end of the tunnel which would keep construction traffic out of the village of North Queensferry for the majority of the work.

Another advantage of the lightweight blocks was that they could be delivered in large lorryloads, significantly reducing the number of required vehicle movements.

Once offloaded, the blocks were passed down the access shaft and transported along the tunnel to the work face hooked onto a specially designed sliding monorail system.

The tunnel was first lined with a hydrocarbon-resistant membrane. Then 21,342 EPS blocks were literally walked into place and arranged to allow safe working at height.

Once the tunnel was infilled, the access shafts were filled with concrete to seal the tunnel and prevent damage to the blocks.

The job was completed by late March, said Mark Arndt, Amey’s operating company representative for the Forth Bridges Unit. “This has been an unusual project,” he said. “It’s a real measure of success that most local residents were not even aware this work was taking place, despite the tunnel emerging within metres of homes in North Queensferry.”

Before sealing the access shafts, local primary schoolchildren filled two time capsules with items of their choice which were then buried among the blocks. Unlike concrete or aggregate material, EPS blocks are easily removed if the tunnel needs to be reopened.

For more information on companies in this article

Related Content

  • Towers of power: California’s Gerald Desmond Bridge Replacement
    May 8, 2019
    Challenging ground conditions meant a design rethink - and some engineering firsts - for California’s Gerald Desmond Bridge Replacement Project* The Port of Long Beach on Terminal Island south of Los Angeles is the second-busiest container port in the US. It handles around 15% of all imported goods, much of it with Asia. As the Port of Long Beach was growing in importance over the past half century, the 51-year-old Gerald Desmond Bridge has faithfully been delivering thousands of daily commuters to wo
  • Amey wins Forth Bridge deal
    December 2, 2014
    Amey will handle the contract to manage and maintain the existing Forth Road Bridge and the new Queensferry Crossing. The latter is currently under construction. The contract will commence on the 1st June 2015 and Amey will then take over responsibility for the Forth Road Bridge, which opened to traffic in 1964. The Queensferry Crossing is due to open to traffic in 2016.
  • Uretek delivers voided soils treatment for UK’s M3 Smart Motorway
    February 8, 2018
    Ground engineering specialist Uretek has been treating voided soils as part of maintenance following completion of the UK’s M3 Smart Motorway project. Work is between junctions 2 and 4a where Uretek has provided a non-disruptive alternative to conventional underpinning to solve foundation subsidence problems. The focus for Uretek is an old 900mm corrugated pipe, 73m long. The old pipe has had a new 700mm pipe inserted inside. However, the old pipe is rusting and rapidly deteriorating.
  • Storstrom Bridge to be Denmark’s third longest
    March 8, 2018
    Form and functionality come together in Denmark’s latest Storstrom Bridge design. David Arminas reports. An Italian joint venture recently won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate - Vejdirektoratet - awarded the work to a joint venture of Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 milli