Amey chooses polystyrene blocks for Scottish tunnel infill

Amey recently completed an infill project to make safe a disused railway tunnel underneath the approach roads north of Scotland’s Forth Road Bridge. The 420m tunnel was part of the Dunfermline to North Queensferry railway line that provided a link to the ferry service until the opening of the Forth Bridge in 1890. The 4.3m-wide and 5.1m-high tunnel with vaulted roof and brick lining continued in use for freight until 1954. The tunnel runs underneath the A9000 and B981 on the northern approach to the Forth
June 25, 2018 Read time: 3 mins
Amey made light of the project by using expanded polystyrene (EPS) blocks
Amey recently completed an infill project to make safe a disused railway tunnel underneath the approach roads north of Scotland’s Forth Road Bridge.


The 420m tunnel was part of the Dunfermline to North Queensferry railway line that provided a link to the ferry service until the opening of the Forth Bridge in 1890. The 4.3m-wide and 5.1m-high tunnel with vaulted roof and brick lining continued in use for freight until 1954.

The tunnel runs underneath the A9000 and B981 on the northern approach to the Forth Road Bridge. Both tunnel ends had been sealed and the adjacent cuttings filled in, leaving a vertical shaft at each end as the only access points.

An 2958 Amey inspection had found parts of the tunnel degrading and in need of preventative maintenance to ensure continuing structural integrity. Due to the limited depth of cover above the tunnel, a failure could have had an impact on the roads overhead.

Two options were considered: an ongoing programme of inspection and maintenance or a one-off project to infill the tunnel with a low-cost material. The infill option was chosen because it would eliminate the need for future inspections or maintenance making it the more cost-effective solution in the long term.

After considering workforce safety, overall cost and the need to avoid disruption to the local community, it was decided to fill the tunnel with expanded polystyrene (EPS) blocks. These were manufactured to a specific compressive strength capable of resisting the weight of rock and tunnel lining in the event of a localised structural failure.

The EPS blocks were pre-cut to a size and weight to facilitate easy manual handling on-site. This allowed work to be carried out from the access shaft at the north end of the tunnel which would keep construction traffic out of the village of North Queensferry for the majority of the work.

Another advantage of the lightweight blocks was that they could be delivered in large lorryloads, significantly reducing the number of required vehicle movements.

Once offloaded, the blocks were passed down the access shaft and transported along the tunnel to the work face hooked onto a specially designed sliding monorail system.

The tunnel was first lined with a hydrocarbon-resistant membrane. Then 21,342 EPS blocks were literally walked into place and arranged to allow safe working at height.

Once the tunnel was infilled, the access shafts were filled with concrete to seal the tunnel and prevent damage to the blocks.

The job was completed by late March, said Mark Arndt, Amey’s operating company representative for the Forth Bridges Unit. “This has been an unusual project,” he said. “It’s a real measure of success that most local residents were not even aware this work was taking place, despite the tunnel emerging within metres of homes in North Queensferry.”

Before sealing the access shafts, local primary schoolchildren filled two time capsules with items of their choice which were then buried among the blocks. Unlike concrete or aggregate material, EPS blocks are easily removed if the tunnel needs to be reopened.

For more information on companies in this article

Related Content

  • Upgrade for Scottish road
    February 17, 2012
    Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between
  • Scottish trial for OTT HydroMet’s ecoLog 1000
    April 25, 2022
    An OTT ecoLog 1000 water level logger with cellular data connection to Hydromet Cloud was trialled upon the Vales Burn Bridge in Scotland.
  • New M90 surfacing in the UK gain praise
    January 8, 2013
    Early evaluation of surfacing work on the M90 at Rosyth – the first major application of Scotland’s new TS2010 specification – has earned positive praise. Transport Scotland’s determination to obtain pavement that is durable, long lasting and safe (especially in early life) is clearly apparent on the M90 just north of the Forth Road Bridge. Here surfacing has been carried out this spring to TS2010, a tough new specification designed to ensure thin surfacing pavements that work. And the initial prognosis is
  • Micro surfacing the Brooklyn Bridge with Bergkamps’ M210 paver
    May 16, 2018
    A major job for micro surfacing took place on the Brooklyn Bridge near New York. It was the third time in Ken Messina’s career that he would provide micro surfacing for the iconic Brooklyn Bridge, built in 1883. Messina, as president of New Jersey-based Asphalt Paving Systems (APS), knew only too well the challenges that lay ahead. And there were many. There would be only a brief window of opportunity for paving, with lane closures starting at 10pm and ending at 5am. The cool, humid atmosphere would a