UK’s A14 upgraded route opening early

A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times. Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by
October 14, 2019 Read time: 2 mins
The full A14 upgrade project remains on track to open to traffic by the end of 2020
A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times.


Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by the A14 Integrated Delivery Team, a joint venture between 1146 Balfour Beatty, 2319 Costain and 2296 Skanska, and design consultants 3005 Atkins and 2874 CH2M.

The project also won four awards at the 2019 British Construction Industry Awards. These were Digital Transformation Initiative of the Year, Productivity Initiative of the Year, Partnership Initiative of the Year and Initiative of the Year Award.

The new link will boost access between the region’s ports and the West Midlands – a key logistics hub. On completion, the road will open as an A road, instead of a motorway as originally planned. This will take advantage of wider lanes when joining the neighbouring M11 and A1(M).

The early delivery of the project will mean that work will commence sooner on the planned improvements to local roads in and around Huntingdon and the dismantling of the old viaduct over the train station.

For more information on companies in this article

Related Content

  • Importance of road/tunnel drainage systems
    April 10, 2012
    A variety of systems are available for quickly and efficiently removing water from roads as Patrick Smith reports The presence of water in a highway layer reduces the bearing capacity of the road, and in doing so it also reduces the structure's lifetime. Indeed, the recent extremely cold winter in many parts of Europe has shown that in colder climates there is a risk of frost damage when water is present resulting in costly potholes, so drainage systems performing properly are important in road design.
  • Importance of road/tunnel drainage systems
    May 8, 2012
    A variety of systems are available for quickly and efficiently removing water from roads as Patrick Smith reports. The presence of water in a highway layer reduces the bearing capacity of the road, and in doing so it also reduces the structure's lifetime. Indeed, the recent extremely cold winter in many parts of Europe has shown that in colder climates there is a risk of frost damage when water is present resulting in costly potholes, so drainage systems performing properly are important in road design.
  • One of Brazil’s main road routes will be upgraded
    November 16, 2012
    Brazil’s Ministry of Transportation is giving the go-ahead for a project that will see the upgrade of a 100km stretch of the BR-381 route. Located in Minas Gerais, the BR-381 will be widened and improved with the addition of extra lanes, making it a dual carriageway. The Ministry of Transportation has opened the first phase of the project to bids and bids have to be submitted before December 17th 2012.
  • CS involved in two tolling and ITS projects in Poland
    May 14, 2012
    French company CS Communication & Systèmes has announced it has delivered the Poland A1 Phase 2 tolling and ITS project two months ahead of schedule. Earlier this year, Intertoll, the prime contractor of the project, asked CS to accelerate the project that was initially expected to be completed on 21 December, 2011. The scope of this project included the design, supply, installation and maintenance of six toll plazas, 16 automated entry lanes and 23 manual exit lanes. CS also designed and installed a full I