UK’s A14 upgraded route opening early

A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times. Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by
October 14, 2019 Read time: 2 mins
The full A14 upgrade project remains on track to open to traffic by the end of 2020
A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times.


Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by the A14 Integrated Delivery Team, a joint venture between 1146 Balfour Beatty, 2319 Costain and 2296 Skanska, and design consultants 3005 Atkins and 2874 CH2M.

The project also won four awards at the 2019 British Construction Industry Awards. These were Digital Transformation Initiative of the Year, Productivity Initiative of the Year, Partnership Initiative of the Year and Initiative of the Year Award.

The new link will boost access between the region’s ports and the West Midlands – a key logistics hub. On completion, the road will open as an A road, instead of a motorway as originally planned. This will take advantage of wider lanes when joining the neighbouring M11 and A1(M).

The early delivery of the project will mean that work will commence sooner on the planned improvements to local roads in and around Huntingdon and the dismantling of the old viaduct over the train station.

For more information on companies in this article

Related Content

  • Long-lasting surface repairs for Avonmouth Bridge
    July 9, 2012
    Two technologies combined to give a heavily used bridge a new surface that should last for years The Avonmouth Bridge carries the M5 motorway over the River Avon, and is a vital part of the road infrastructure in south-west England, linking the counties of Somerset, Devon and Cornwall to the rest of the country. Completed in 1973, it carries commuters to the city of Bristol, and to South Wales, along with holidaymakers. The 1.4km long steel box girder bridge comprising a 16,000m2 steel decked central span a
  • New funding for 44 infrastructure projects
    December 26, 2024
    New funding awards escalate the launch of 44 major infrastructure projects.
  • Stonehenge tunnel going ahead?
    September 12, 2017
    The preferred route has been announced for a new road and tunnel link on the A303 route in the UK that will bypass the famous Stonehenge stone circle. The project now finally looks as if it might go ahead after years of debate, although several hurdles have yet to be passed. The work calls for the construction of a new 13km dual carriageway link and includes a 2.6km stretch of tunnel. The new route will be located further away from Stonehenge and the tunnel is being built
  • Tenders open for England’s A66 northern trans-Pennine route
    October 31, 2019
    A €52 million contract to design the transformation of the A66 northern trans-Pennine route in England is now up for grabs, according to Highways England. A tender is open for dualling the remaining single carriageway sections of the A66 which links the M6 motorway at Penrith in Cumbria and the A1(M) motorway) at Scotch Corner in North Yorkshire. The formal notice for the A66 Preliminary Designer, Construction Technical Advisor and Supervision tender process has been published in the Official Journal of