UK’s A14 upgraded route opening early

A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times. Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by
October 14, 2019 Read time: 2 mins
The full A14 upgrade project remains on track to open to traffic by the end of 2020
A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times.


Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by the A14 Integrated Delivery Team, a joint venture between 1146 Balfour Beatty, 2319 Costain and 2296 Skanska, and design consultants 3005 Atkins and 2874 CH2M.

The project also won four awards at the 2019 British Construction Industry Awards. These were Digital Transformation Initiative of the Year, Productivity Initiative of the Year, Partnership Initiative of the Year and Initiative of the Year Award.

The new link will boost access between the region’s ports and the West Midlands – a key logistics hub. On completion, the road will open as an A road, instead of a motorway as originally planned. This will take advantage of wider lanes when joining the neighbouring M11 and A1(M).

The early delivery of the project will mean that work will commence sooner on the planned improvements to local roads in and around Huntingdon and the dismantling of the old viaduct over the train station.

For more information on companies in this article

Related Content

  • UV lining is highway drainage first for UK motorway upgrade
    December 19, 2017
    Drainage specialist Lanes Group is implementing the first project to extensively line highway drainage pipes as part of a Smart Motorway initiative in the UK. Lanes has been commissioned by the Carillion Kier Joint Venture working for Highways England to install ultra-violet – UV - liners during the M6 Junction 16-19 Smart Motorway scheme between Crewe and Knutsford, in county Cheshire. Lanes said that it is the first time that roadside drainage pipes will have been extensively lined, instead of being
  • Formwork solutions for bridge maintenance and repair
    January 6, 2015
    An array of innovative formwork solutions have helped in the repair and construction of key bridge links - Mike Woof writes Formwork producers are continually developing novel solutions for bridge maintenance and construction applications. Several key structures have benefited from the novel use of formwork systems, with suppliers such as Doka, PERI, Pilosio and RMD all working on important structures in recent times. In Estonia, construction work is underway on the bypass around Tartu, the country’s
  • Work to start on triple-deck roundabout in North Tyneside, UK
    June 30, 2016
    Construction of a major triple-deck roundabout in North Tyneside, England starts in August.

    The roundabout is part of an upgrade to the A19/A1058 Coast Road junction that includes lowering the A19 beneath the existing A1058 Coast Road and roundabout.

    The €90 million scheme is on the main route to and from the Tyne Tunnel and will mean that people travelling along the A19 will no longer have to queue at the roundabout to go continue their journey straight ahead. Instead, drivers will use a new section of road which will run under the junction.
  • UK M6 motorway project complete
    December 20, 2024
    Work for the UK’s M6 motorway upgrade project is complete.