UK’s A14 upgraded route opening early

A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times. Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by
October 14, 2019 Read time: 2 mins
The full A14 upgrade project remains on track to open to traffic by the end of 2020
A key section of the UK’s important A14 upgrade project is opening to traffic ahead of schedule. Work to deliver the new stretch of dual carriageway for the A14 bypass is being completed a full 12 months early. The bypass section will open to drivers in December 2019, cutting congestion and journey times.


Work on the 19km bypass section commenced in October 2016 and forms part of a programme of 33.6km of road works in Cambridgeshire, costing £1.5 billion. The road building project has been carried out by the A14 Integrated Delivery Team, a joint venture between 1146 Balfour Beatty, 2319 Costain and 2296 Skanska, and design consultants 3005 Atkins and 2874 CH2M.

The project also won four awards at the 2019 British Construction Industry Awards. These were Digital Transformation Initiative of the Year, Productivity Initiative of the Year, Partnership Initiative of the Year and Initiative of the Year Award.

The new link will boost access between the region’s ports and the West Midlands – a key logistics hub. On completion, the road will open as an A road, instead of a motorway as originally planned. This will take advantage of wider lanes when joining the neighbouring M11 and A1(M).

The early delivery of the project will mean that work will commence sooner on the planned improvements to local roads in and around Huntingdon and the dismantling of the old viaduct over the train station.

For more information on companies in this article

Related Content

  • More tenders for the Lower Thames Crossing
    April 2, 2021
    The winners will build 23km of road connecting to what will be the UK’s longest road tunnel.
  • Consultation soon for Vancouver area’s Massey Tunnel replacement
    September 19, 2019
    The Canadian province of British Columbia could put options for a Massey Tunnel replacement out to consultation late this year or early next. A statement from the BC ministry of transportation and infrastructure said the government is in discussions with various stakeholders about which options it will put out for consultation. Whatever option is chosen to replace the ageing four-lane Massey Tunnel – be it a bridge or another tunnel – it will be will be either six or eight lanes, according to the gove
  • Algeria bypass project underway
    December 1, 2015
    Work is now underway on a series of projects in Algeria, including the East West Highway and a key highway bypass. The 67km Khémis Miliana-Berrouaghia bypass is expected to cost around US$836 million, with work due for completion at the end of 2016. The project is being handled by an Algerian/Italian team.
  • Brisbane's highway of distinction
    August 2, 2012
    A massive AU$2 billion update of the Gateway Motorway in Queensland is underway to improve an infrastructure stretched by population boom. Report and photographs by Adrian Greeman Just 20 years after the Australian city of Brisbane built its Gateway Motorway with a high slim signature bridge dominating the river skyline, the road is being completely revamped. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels; the north is getting a completely