Three Colombian bridge projects commencing

In Colombia progress is being seen on three major bridge projects located in different parts of the country. Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished. The new
January 17, 2019 Read time: 3 mins

In Colombia progress is being seen on three major bridge projects located in different parts of the country.

Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished.

The new bridge provides a height of 45m over the Magdalena River, allowing vessels to pass underneath. When complete the bridge will be Colombia’s longest and will provide a new link between Santa Marta and Baranquilla.

Constructed in 1974, the old bridge has restricted river traffic due to its low height and is too narrow to cope with the vehicle numbers it has to carry. Its design prompted controversy even when it was built but the new link will address the transport shortcomings over the earlier structure.

Meanwhile, construction work will restart on the Chirajara Bridge in the second quarter of 2019. The French contractor 5871 Eiffage will carry out the work, which is expected to cost US$31.7 million. Construction work on the bridge was halted in January 2018 after part of the structure collapsed. The project is being managed by Concesionaria Vial de los Andes (Coviandes)

At the same time, concern has been expressed over the Hisgaura Bridge as to its safety. The $33 million project is being carried out by Spanish contractor Sacyr. Although the bridge is said to be safe, its construction does not meet the requirements of the agreement set by Colombian funding agency Fondo Adaptacion. The problems is with the central span, which rather than being flat now has an uneven, undulating deck. It is not clear how this issue occurred during construction or how best to alleviate the problem. But Colombia's national road institute (Invias) is less than impressed and is now looking to gain compensation from Sacyr over the Hisguara Bridge project as a result.

The bridge forms part of the Málaga—Los Curos highway, which will improve transport between Colombia’s Boyacá Region and Santander Region. The Hisgaura Bridge measures 653m in length with a single span reaching 400m.

There has also been criticism over the poor standard of the access roads to the Hisgaura Bridge. But paving work is now underway on 70km of access roads and this will be completed by 2020. Work to the remaining 50km will be finished at a later date.

For more information on companies in this article

Related Content

  • Increased costs for new Duisburg bridge
    June 2, 2020
    Increased costs are now being anticipated for the new Duisburg bridge project.
  • Colombia bridge collapse closes route stretch
    January 22, 2018
    A bridge on Colombia’s Bogota-Villavicencio collapsed with the deaths of 10 personnel. This has caused the closure of the route close to the El Naranjal tolling area to all but emergency vehicles. in Meta department. The Chirajara Bridge forms part of the project to construct the road to connect capital Bogota with Villavicencio. The National Infrastructure Agency (ANI) held an emergency meeting with road concessionaire Coviandes, which is managing the project to construct the bridge.
  • Project building new Biobio bridge in Chile on track
    August 28, 2014
    Construction work on the fourth bridge spanning Chile’s Biobio Bridge is proceeding on schedule. The project site is located in Chile’s Gran Concepcion area. Construction could commence in 2016, with completion expected in 2018. Environmental studies have yet to be completed however. The work will be carried out as part of a concession package and the bridge is expected to cost some US$214 million to construct, carrying two lanes for vehicle traffic as well as claiming pedestrian and cycling connectivity. T
  • Meva’s Mammut 350 formwork makes the difference for Neckar viaduct
    April 19, 2018
    Formwork specialist Meva is helping replace the longest motorway bridge, the Neckar River viaduct in Germany’s south-west state Baden-Wuerttemberg Work on the 1.3km Neckar viaduct, part of the A6 motorway at Heilbronn, should be finished by 2022. It is part of the A6 expansion project between the Weinberger junction and Wiesloch/Rauenberg. The project is officially the new Neckar viaduct BAB 6 at Heilbronn. Federal Motorway 6, the A6, is also known as the BAB 6. The 477km motorway starts at the French b