Sunderland’s Northern Spire bridge opens

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather. The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project. Work began in May 2015 and the bridge has been built within its allocated €129 million budget. However, poor weather conditions pushed back the opening of the bridge from this past
August 28, 2018 Read time: 2 mins
Aspiring spire: The Northern Spire’s 105m-high central A-frame pylon highlights the Sunderland project

Sunderland’s Northern Spire bridge with its 105m-high central A-frame pylon opens to traffic today after a four-month delay because of poor weather.

The bridge opened for pedestrians and cyclists yesterday after three Sunderland-built Nissan vehicles first crossed the bridge during a ceremony to mark completion of the project.

Work began in May 2015 and the bridge has been built within its allocated €129 million budget.

However, poor weather conditions pushed back the opening of the bridge from this past spring, said Mark Jackson, Sunderland City’s head of infrastructure and transportation. Particularly affected was the painting of the pylon, which needed very still, dry, calm conditions, both for the painting and the use of high-level working platforms required by the painting team.

The 336m-long two-span cable-stayed bridge across the River Wear has four vehicle lanes, as well as dedicated cycle and pedestrian routes. The steel and concrete bridge is part of 2.8km of new road layout.

Steel specialist Victor Buyck spent a year fabricating the pylon at its canal-side yard in Ghent, Belgium. Apart from the 1,550tonnes tonnes of steel, around 550tonnes of concrete went into making the pylon that, because of its size, had to be constructed in the open air. It was barged across the often-treacherous North Sea to Sunderland.

World Highways has been following construction of the project, including the manufacturing, transport and raising of the main pylon.
http://www.worldhighways.com/categories/road-highway-structures/features/sunderlands-new-wear-crossing-takes-shape/

The construction contract was awarded to FVB, an international joint venture set up by Farrans Construction and Victor Buyck Steel Construction. Farrans Construction operates as a building and civil engineering contractor across the UK and Ireland. Victor Buyck, based in Belgium, is one of Europe's major structural steelwork contractors, specialising in steel bridges.

FVB has been supported by its design team led by Buro Happold Engineering and Roughan & O'Donovan. Independent checker has been Ramboll.

Related Content

  • Stirling Lloyd in the fast lane: Waterproofing Warsaw’s Rowecki Bridge
    January 19, 2016
    Warsaw’s General Stefan Rowecki Bridge, or the Grota Bridge, is the second largest in the Polish capital and, as part of the Trasa Toruska expressway, it is the busiest. The structure, which opened in 1981, handles 150,000 cars daily, so repairs were always going to be tricky if minimal disruption to traffic was to occur. The steel orthotropic deck consists of two structurally independent parts – each with four traffic lanes. This meant that pedestrians and cyclists were restricted to two very narrow track
  • Norway drops tender plans for second Sotra fixed link
    February 18, 2019
    Statens Vegvesen, the Norwegian Road Administration, has cancelled tender plans for a new Sotra fixed link project that were scheduled for the spring. Jon Georg Dale, minister of transport, recently told the Norwegian Parliament that the geology near Lake Storavatnet along the route of the project, of which the second bridge would be a part, has caused concern among planners. Also, reconstruction of a high-voltage power cable has come under questions. Helge Eidsnes, a regional manager of Statens Vegve
  • Stantec: coming to an infrastructure site near you
    April 13, 2017
    Acquisitive Canadian firm Stantec is snapping up more transportation expertise as it moves out of its home North American market. David Arminas reports. Last December, politicians from the US states of Kentucky and Indiana celebrated the opening of the second of two major bridges. A ribbon-cutting ceremony took place in cold wintry weather on the new 762m-long cable-stayed Lewis and Clark Bridge. The event marked the finish of the prestigious three-and-half-year Ohio River Bridges Project.
  • Delayed Houston Ship Canal Bridge nearing first phase
    February 23, 2024
    The delayed Houston Ship Canal Bridge is nearing its first phase completion.