SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Ramboll appointed independent engineer on Champlain Bridge Project
    September 8, 2015
    Ramboll has been appointed independent engineer for the planned Champlain Bridge Corridor project in Montreal, Canada. Ramboll, based in Denmark, will work with the Canadian consultant Stantec to review the design and construction schedule of the entire length of the bridge corridor, one of the largest infrastructure projects in North America. Stantec will review of all highway design along with site inspections for the project that will cross the St. Lawrence River and cost up to US$4.1 billion. “The ne
  • SSL hits back over criticism of its work on the Champlain Bridge
    December 11, 2017
    The contactor building the replacement Champlain Bridge in Canada has hit back over of allegations of poor workmanship in the US$3.3 billion project. The new 3.4km cable-stayed Champlain Bridge over the St Lawrence River will have six lanes vehicle lanes and a separate cycle and pedestrian lane. Design life is 125 years and is being constructed under a public-private partnership and operating contract of 30 years after completion of construction. Work includes construction of a smaller bridge for Île des
  • JCCBI says US$300m for demolishing Montreal’s old Champlain Bridge
    April 11, 2017
    Tearing down the old steel truss cantilever Champlain Bridge in Montreal could cost around US$300 million, according to preliminary estimates by a federal government agency. Also, until the nearby new Champlain Bridge is finished, it will cost US$93 million annually to maintain the old one, according to Jacques Cartier and Champlain Bridges Incorporated (JCCBI), the federal Canadian agency that oversees several major road infrastructure assets in the city. Dismantling will start in 2019 at the earliest and
  • Canada: Champlain Bridge deal awarded to SNC-Lavalin consortium
    April 17, 2015
    The Canadian government has awarded a multi-billion dollar contract for the Champlain Bridge in Montreal, in the province of Quebec, to a consortium led by SNC-Lavalin. The firm, based in Montreal, will design, build, maintain and operate the toll bridge under a 35-year public-private partnership deal worth between US$2.5-$4.1 billion. The consortium called Signature on the Saint-Lawrence Group includes Spanish firms Dragados Canada and ACS Infrastructures and the US firm Flatiron Construction. Other