SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Hyundai E&C is working on Turkey’s new third Bosporus Bridge
    July 10, 2013
    Hyundai Engineering & Construction (Hyundai E&C) is to head a consortium building the lateral towers, aprons and suspension cables for the new Bosporus crossing in Turkey. Hyundai E&C will work in a consortium with its partner SK Engineering & Construction on the US$697 million project to construct the 2.16km Third Bosporus Bridge. This suspension bridge will feature eight lanes for motor vehicle traffic as well as two rail lines. With a width of 59m it will be the widest bridge in the world that carries a
  • London’s congestion charge is saving lives, a study suggests
    March 9, 2015
    Traffic accidents in the UK capital London have declined 40% since the introduction of a congestion charge in 2003, according to a new study. The number of accidents per million miles driven in the congestion zone fell to 2.6 accidents per million miles from an average of 12.4 before the introduction of the charge. Researchers at Lancaster University also found a similar fall in the number of people seriously injured or killed. As well, accident rates fell in adjacent areas as a result of fewer motorists dr
  • Underground expansion pushes tunnelling market
    June 13, 2012
    Infrastructure investment means that the road tunnel construction sector is healthy due to demand for new links – Mike Woof reports With many emergent nations investing heavily in infrastructure, the tunnelling sector is seeing extensive business at present. Tunnels provide key links in mountainous areas or in congested cities where building roads on the surface may not be practical. In Asia and Latin America, many key road connections are now being built underground to pass challenging terrain or provide
  • Cost rises again for Columbia’s unfinished La Linea tunnel
    February 3, 2015
    Columbia’s transport minister has said it will take nearly US$168 million and more than two years to finish the controversial La Linea tunnel. Natalia Abello Vives said the government has a “plan B” to finish the 8.65km tunnel, which, as World Highways reported in May, has less than a kilometre remaining to be constructed. It was originally scheduled to be open by last November. The La Linea tunnel project, or Segundo Centenario tunnel, crosses the central mountain range and forms part of the Bogota-B