SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Germany to cut red tape for bridge construction up to 2027
    October 5, 2017
    The German federal government has set aside €4.5 billion for refurbishment of 400 bridges in the state of North Rhine-Westphalia up to 2027. Hendrik Wüst, North Rhine-Westphalia transport minister, made the announcement which included around €200 million for road maintenance. The Federal German government also plans to fast-track planning for infrastructure projects. Bonuses to contractors for improved performance to reduce down-time on construction sites as well as the possibily of a six-day working
  • T.Y Lin International to start project management of fourth canal bridge
    June 2, 2016
    The president of Panama, Juan Carlos Varela, has given the green light to T.Y Lin International to start project managing construction of a fourth bridge over the Panama Canal. The US-based infrastructure engineering company won an international tender for the work likely to cost around US$17 million, according to local media. Pre-qualification has started for companies interested in participating on the billion-dollar project. The new bridge is one of three infrastructure projects within a five-ye
  • FCC Corredor de las Playas wins Panama Inter-American Highway deal
    November 21, 2017
    The consortium FCC Corredor de las Playas I has won the contract to widen the first section of the Inter-American Highway. FCC Corredor de las Playas I consists of FCC Construcción and CICSA – the infrastructures and construction division of the Grupo Carso. The Inter-American Highway will be widened along nearly 38km to six lanes between La Chorrera and Santa Cruz in the province of Panama Oeste in Panama at a cost of around US$543 million, according to the consortium. The project includes enlarging the
  • Canadian air
    February 8, 2012
    Compressors from Atlas Copco are proving highly useful in highly diverse applications, on a bridge project and a quarry in Canada. Water ingress over 30 years has damaged a road bridge in Quebec City, Canada, deteriorating the concrete and breaking down the rubber expansion joints at both ends of the 150m long structure. City highway authority, Transportes Quebec, awarded local contracting company Inter-Structures the contract to replace the deteriorated concrete and fit new membrane seals. The bridge, clos