SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • 2015 IRF Global Road Achievement Awards Laureate
    September 15, 2015
    Commuter traffic in the Taipei Metropolitan Area is a major concern for the city’s town planners. In 2009, a decision was reached to widen National Freeway No. 1 between Wugu and Yangmei on a 42km section of freeway on the northern part of town. The lane-widening project saw the construction of two new viaducts built along each side of the freeway. From the onset, the project presented tremendous challenges owing to various factors, including limited space for construction; passing through a geologically
  • Vietnam province to spend US$2.77bn on transport infrastructure over next 8 years
    April 24, 2012
    Long An province in Vietnam will see US$2.77billion spent on constructing and improving its inner waterway and road infrastructure over the next eight years. The provincial peoples’ committee (PPC) revealed that the major capital project will include the construction of bridges and roads linking central areas and towns. The new roads will stretch around 400km and new dredge waterways will span 600km on the Chanh, Thu Thua, Bac Dong and Tra Cu canals by 2015. Small wharves and Long An Port will also be estab
  • Work zone safety solution on busy world highways
    December 3, 2013
    Globally renowned highway work zone safety solution manufacturers have been providing some of their latest systems to protect roadworkers and motorists on high volume traffic highways. Guy Woodford reports Versilis has provided one of its state-of-the-art work zone safety solutions during the rehabilitation of North America’s busiest highway. The Canadian road safety product innovator and manufacturer was retained by the Ministry of Transportation of Ontario (MTO) to install automated traffic control
  • Solving congestion in Brisbane
    August 2, 2012
    Rapid growth in a major Australian city in recent years has created new problems for the infrastructure and especially transport Expansion in the city of Brisbane, the Queensland state capital and the third largest city in the country, is set to continue and some 1,500 people arrive/week from within Australia and from other parts of the world. At this rate by 2026 the city's population should increase by 1.4 million: at present it is 1.8 million. To cope, the Queensland government and city council have ini