SSL settles legal issues, Champlain Bridge to open December 21

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
April 18, 2018 Read time: 2 mins
Merry Christmas to Montreal: Champlain Bridge replacement opens in December

Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium.

The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports.

Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the St Lawrence River and Seaway canal would open in December but gave no date. The December 21 date it newly three weeks later than planned.

Failure to open the 3.4km-long bridge to vehicular traffic on time means the consortium would face stiff fines, according to media reports: around $77,500 a day for the first seven days followed by $310,000 per day.

No details of the settlement were released.

Cost of the entire 6km corridor project is set at US$3.3 billion of which around $1.8 billion is for construction of the bridge, approach roads and highway adjustments.

The federal Canadian government signed a public-private partnership deal with the SNC-Lavalin consortium Signature on the Saint-Laurent Group in mid-2015 for the group to design, build, finance and maintain the New Champlain Bridge Corridor project. SNC-Lavalin is a 50% partner in SSL which will operate and maintain the bridge until October 2049. Other SSL partners are Hochtief, Flatiron, Dragados Canada and Grupo ACS.

Meanwhile, SSL entered into a date-certain, fixed-priced contract with a construction joint venture of which SNC-Lavalin is again a 50% partner.

The new bridge has six vehicle lanes plus two lanes running in the middle of the bridge for electric public transit trains. The bridge runs from the Ile des Soeurs to Brossard, immediately downstream from the existing Champlain Bridge.

Every year, around 50 million vehicles cross the old bridge, Canada’s most heavily travelled bridge and a major route for traffic to and from the US. Construction of the existing steel truss cantilever bridge, as well as accompanying approaches and the Bonaventure Expressway, started in 1957 and finished in 1962. Of the old 14.5km-long complex, the bridge is 7.4km.

Related Content

  • Vancouver’s 10-lane bridge replacement for Massey Tunnel remain undecided
    October 23, 2015
    Construction of a 10-lane bridge to replace a congested river tunnel in Vancouver, Canada, is still on target to start in 2017, despite details remaining sketchy.

    The bridge will replace the 60-year-old George Massey Tunnel between the local cities of Richmond and Delta along the provincial Highway 99. But the cost and – importantly – whether it will be a toll bridge have not been declared by the British Columbia provincial government.
  • Times they are a changing
    July 23, 2012
    Construction in China still appears to be on course for growth even with the gloomy economic outlook, as it enjoys "a strong budgets position." Patrick Smith reports One thing is certain in the current global economic climate: nothing is certain. And while China has not been unaffected by the economic events of recent months it has, according to Robert Zoellinck, president of the World Bank, a very strong current account and budgetary position. For some years, the nation has enjoyed double digit growth (the
  • Demolition of Seattle’s Alaskan Way Viaduct has started
    February 28, 2019
    Demolition has started on downtown Seattle’s old Alaskan Way Viaduct as part of a major waterfront redevelopment project that included the State Route 99 tunnel. According to Seattle media, Washington state is aiming to collect US$200 million in tolls from the 3.2km tunnel – which is now open - as part of the $3.3 billion replacement of the Alaskan Way Viaduct. However, tolling on the double-deck tunnel which has two lanes in each direction, plus an eight-foot safety shoulder, will not start until this s
  • Paraguay bridge project faces issues
    February 25, 2021
    A Paraguayan bridge project is facing controversy.