Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • SSL settles legal issues, Champlain Bridge to open December 21
    April 18, 2018
    Montreal will get its new Champlain Bridge just before Christmas, a date agreed upon by the Canadian government and the SNC-Lavalin-led consortium. The agreement settles an outstanding lawsuit that the Consortium had filed regarding costs increases of around US$186.5 million relating to the transportation of oversized parts and delays to the bridge's construction, according to media reports. Last month SNC-Lavalin, head of the Signature on the Saint-Laurent Group (SSL), had said that the bridge over the
  • Further delays expected for the Fehmarn Belt Fixed Link
    August 26, 2015
    Further delays to the planned Fehmarn Belt Fixed Link between Germany and Denmark appear likely because of objections to the project during the planning stages, Danish media reported. Government authorities in the German state of Schleswig-Holstein indicated that permission for the project, which focusses on a 17km immersed road and rail tunnel, will probably be given in 2017, and not next year as previously believed. German authorities have received about 3,100 objections to the project that has rise
  • Delays to highway, tunnel and bridge building
    May 14, 2012
    The Slovakian government is being asked for financial compensation by Granvia, the group building the country’s new Nitra-Banska Bystrica highway. Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.
  • JP Autoceste eyes 2020 as completion date for Bosnia’s Corridor 5c
    March 3, 2016
    Around two-thirds of the Corridor 5c motorway project is expected to be completed by 2020, according to the director of the Bosnian motorways company JP Autoceste. Jasmin Buco said that 120km out of 337km of the motorway are complete. The corridor section, to connect Budapest with Ploce port in Croatia, is taking the most time. He said that the cost of the remaining part of the motorway is expected to be around €2.81 billion.