Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • Green light for D35 Litomysl-Janov bypass
    August 15, 2023
    Czech transport ministry aims for construction to start next year on the 10.3km section of motorway, part of the pan-European TEN-T road network.
  • Turkey to tender for Izmir-Candarli beltway contract
    November 15, 2016
    Turkish highway authorities will tender construction of the remaining part the Izmir-Menemen-Aliaga-Candarli motorway on 15 February. The contract will be build-operate-transfer for the 76km section between the towns of Aliaga and Candarli. Constructions is expected to take three years. The 16km section between Izmir and Menemen is already finished, according to Turkish media. Up to 60,000 vehicles a day are projected to use the highway from Izmir to Candarli. It is officially called the Otoyol 30
  • Penang’s PAN 1 project to go ahead amid environmental concerns
    April 17, 2019
    Malaysia’s Penang state has approved the PAN 1 Highway project but with conditions attached following an environmental impact study. Work could start next year on the 19.5km project – officially called the Pan Island Link 1 - that will likely cost around US$1.7 billion, according to a report in the newspaper Sundaily. The project will consist of 7.6km of viaducts, four tunnel sections totalling 10.1km in length and embankment sections totalling 1.8km. Penang Island, around 300km², is the main islan
  • Delays on Slovakian projects
    July 9, 2012
    Work on several new highways being built in Slovakia as public-private partnerships (PPPs) will be delayed by six to 12 months. This means that the first sections of the Martin-Presov link will not open before 2011. The last section is expected to be completed in either late 2012 or early 2013.