Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • Go-ahead for controversial highway
    May 30, 2012
    APPROVAL HAS now been given for work to go ahead on a key section of Slovakia’s D1 highway. The work had been delayed as the European Commission (EC) was concerned over environmental issues facing sections of the route that passed through a nature reserve. The EC has now given its approval for construction of the highway between Martin and Presov on conditional terms. The EC says that the sections in zones belonging to the Natura 2000 network can be built once terms are agreed with the Slovak government o
  • Slovakia highway projects due for completion
    September 2, 2015
    In Slovakia work on three sections of the D1 highway will be complete shortly. One of these is for a 9km section of the D1 from Janovce -Jablonov, which is built by the Czech firm Bogl and Krysl. A 9.5km section of the D1 from Janovce -Jablonov is being built by Eurovia and will be ready at the end of 2015. The 11.2km section of the D1 from Fricovce - Svinia is being built a consortium comprising Strabag and Doprastav and is scheduled for completion in October 2015. The 10.4km section of the R2 route from P
  • 2015 IRF Global Road Achievement Awards Laureate
    September 15, 2015
    Commuter traffic in the Taipei Metropolitan Area is a major concern for the city’s town planners. In 2009, a decision was reached to widen National Freeway No. 1 between Wugu and Yangmei on a 42km section of freeway on the northern part of town. The lane-widening project saw the construction of two new viaducts built along each side of the freeway. From the onset, the project presented tremendous challenges owing to various factors, including limited space for construction; passing through a geologically
  • Romania retenders Lugoj-Deva section of A1
    April 20, 2022
    The Lugoj-Deva segment has been troublesome, with landslides halting work at least twice.