Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • Boring complete for Slovakian tunnel project
    November 30, 2022
    Tunnel boring is now complete for a major Slovakian tunnel project.
  • Slovakia: early 2017 restart for work on the Cebrat Tunnel
    May 27, 2016
    Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
  • Vahostav-SK and TuCon to build Slovakia’s Presov northern bypass
    July 4, 2019
    Slovak contractors Vahostav-SK and TuCon will build the first stage of the 4.3km northern bypass in Presov on the R4 dual carriageway. The contract was awarded in an open tender by Slovakia’s motorway company NDS. The consortium offered the lowest price of just under €143 million against around €170 million as estimated by NDS which says work will start this summer. NDS also said that it had received five firm bids for the work which will likely take three years and nine months, for completion in 2
  • Slovakia, Salini Impreglio to part ways over D1-Višňové tunnel work
    March 11, 2019
    Slovakia and the Italian-Slovak consortium of Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel. The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed