Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • €261 million Slovakia road works
    July 17, 2025
    A €261 million Slovakia road project is going ahead.
  • Slovakia’s roads and bridges to be improved
    April 15, 2019
    A new plan from Slovakia’s Ministry for Transport and Construction will see upgrade work being carried out to 180km of major roads and 60 or more bridges. A finance package of €200 million has been secured for the work, which will be carried out over the next 36 months. This programme of works is being financed by the OP Integrated Infrastructure (OPII) fund. At present, 122km of dual carriageways and motorways are under construction in Slovakia according to the state-owned road firm NDS. Completion of the
  • Slovakia’s Budimir-Bidovce motorway stretch to open by December
    June 25, 2019
    Slovakia’s 14km stretch of the east-west motorway D1, from Bidovce to Budimir, will open in December, according to the government. Last year, Slovakia’s motorway company NDS and the transport ministry agreed a subsidy of nearly €204 million for the D1 section. The EU is covering 85% of the project cost, while the remaining 15% is covered by the government for construction the Budimir-to-Bidovce stretch, near the city of Kosice. The section, being built by Skanska for almost €237 million, is part of th
  • Slovakia concerned over tenders for D1 Presov and D3 Cadca bypasses
    September 14, 2016
    The Slovakian government is examining bids for two tenders for motorway stretches D1 because of their higher-than-expected costs. The deal involves the Presov West - Presov South stretch and the D3 Cadca, Bukov - Svrcinovec section, according to a report in Pravda. Both projects are bypasses of Cadca, near the border with Poland and the Czech Republic, and Presov in eastern Slovakia. The newly appointed transport minister, Arpad Ersek, review the tenders, the Pravda report said. The Slovak Insti