Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the
December 13, 2017 Read time: 2 mins

Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract.

The consortium of OHL ZS and Vahostav-SK and the National Highway Company (5891 NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel.

As a result, the cost of the D1 section (Hubova to Ivachnova motorway) has risen by €61 million to €227 million.

Work was suspended after a landslide in 2015. The newly estimated opening date of the section is 2022, five years late, according to the Spector newspaper.

Builders will be able to start work on the suspended parts of the motorway - including the Čebrať tunnel, immediately after an environmental impact assessment is finished at the end of January, assuming there are no appeals.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

For more information on companies in this article

Related Content

  • Slovakian road tunnel plan
    January 18, 2023
    Slovakia’s new road tunnel is being planned.
  • Slovak government stands firm over R2 Expressway, including Soroska Tunnel
    August 11, 2017
    Jan Durisin, head of Slovakia’s motorway operator NDS, has said that the R2 expressway, will go ahead despite watchdog fears of poor value for money. Completion of the R2, that includes the Soroska Tunnel, remains 2024, he told Slovakian news agencies. NDS, he said, will start looking for a contractor to start work in 2018 on a stretch of the expressway near the town of Roznava. R2 is a 360km route that will run from Kosice in the east across the country to Trenčín, near the Czech border in the west. It wil
  • Slovakia: Strazov-Brodno D3 route around Zilnia to get EU funds
    May 10, 2016
    The European Union is providing nearly €202 million to finish the section of the D3 motorway between Strazov and Brodno around the city of Zilina in Slovakia. Zilnia is in north-west of Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders. It is the fourth largest city of Slovakia with a population of around 85,000. The D3, formerly D18, is sometimes called the Kysuce Motorway. It was originally to be only a two-lane motorway in the Čadca - Slovak/Polish border
  • Consortium wins Slovakia bypass job
    December 11, 2015
    A consortium will carry out a major bypass project in Slovakia’s capital Bratislava. The consortium comprises Spanish construction firm Cintra, as well as Australian companies Macquarie and Porr. The partners will build part of Bratislava's (Slovakia) ring road. The contract also includes a 30 year management period for a 27km stretch on the D4 motorway and a further 32km stretch on the R7 motorway. The contract will be formalised once all the documentation is verified by the Slovakian Government. The proje