Refurbishing Heathrow road tunnel

A Positioner-Actuator-Manipulator (PAM)machine on hire from UK dealer STM of Tring has been able to cut concrete removal time for Bam Nuttall on its €116.2 million tunnel refurbishment contract at Heathrow Airport. The 18-month contract involves major work on the main and cargo tunnels serving Terminals 1, 2 and 3 in order to comply with the latest European standards and also to extend the life of the tunnels for a further 60 years. As part of the project, some 206m2 of concrete repairs were needed to be
December 11, 2015 Read time: 2 mins
The Canadian built PAM unit was used for the Heathrow Tunnel refurbishment
A Positioner-Actuator-Manipulator (PAM)machine on hire from UK dealer STM of Tring has been able to cut concrete removal time for 3137 Bam Nuttall on its €116.2 million tunnel refurbishment contract at Heathrow Airport. The 18-month contract involves major work on the main and cargo tunnels serving Terminals 1, 2 and 3 in order to comply with the latest European standards and also to extend the life of the tunnels for a further 60 years.

As part of the project, some 206m2 of concrete repairs were needed to be carried out. Bam Nuttall opted to use the Canadian built PAM unit, which allowed work to continue throughout the 10.30 pm to 5.30 am possession time. The breaker is firmly secured to an air-over-hydraulic powered two-piece arm, which isolates vibration from the PAM's controls. The unit is mounted on four castors or removable road wheels and can be pushed into position prior to applying the brake and deploying outrigger legs for stability during operation. Weighing only 525kg without a tool in place, the machine can be easily transported in a conventional van.

For more information on companies in this article

Related Content

  • Lighting innovations boosting brightness, cutting costs
    January 27, 2014
    CU Phosco’s new P850 LED main road lantern has just seen its first major deployment – between Junctions 16 and 17 of the A55, a strategic road which skirts the North Wales coastline – Jason Barnes reports The A55 is a grade-separated dual carriageway also known as the North Wales Expressway. Some 139km long, it originally ran from Chester to Bangor but was extended across the Isle of Anglesey into Holyhead Docks in 2001 under a project part-funded by the European Union.
  • Milling machine developments to boost efficiency
    October 20, 2016
    A series of developments in the milling machine market will give customers both greater choice and performance – Mike Woof writes. Competition is heating up in the market for milling machines, which has been dominated for many years by Wirtgen. The German firm still retains a strong share of this market, but is now facing much tougher levels of competition from key rivals, and Atlas Copco, BOMAG, Caterpillar and Roadtec in particular. Meanwhile the market is also seeing the return of another familiar nam
  • Asphalt paving design advances
    June 15, 2012
    A diverse array of advanced paver designs is now being offered in the asphalt paving sector – Mike Woof reports With the World of Asphalt and INTERMAT 2012 events having both taken place in recent months, a series of innovations have been introduced for the asphalt paving market. Developments have come to market that widen the array of both US and European asphalt paving systems and all the major manufacturers have developed new pavers and materials feeders to meet the latest emissions requirements. Demand
  • Effective stabilisation
    February 24, 2012
    Contractor BAM Nuttall and specialist piling sub contractor Aarsleff Piling, have been working closely to develop a cost-effective solution to a tricky piling problem. The two firms have developed an alternative and versatile technique to reduce the risk of delays installing 2,150 precast concrete piles along part of the route of an innovative guided busway in Cambridgeshire in the UK.