Refurbishing Heathrow road tunnel

A Positioner-Actuator-Manipulator (PAM)machine on hire from UK dealer STM of Tring has been able to cut concrete removal time for Bam Nuttall on its €116.2 million tunnel refurbishment contract at Heathrow Airport. The 18-month contract involves major work on the main and cargo tunnels serving Terminals 1, 2 and 3 in order to comply with the latest European standards and also to extend the life of the tunnels for a further 60 years. As part of the project, some 206m2 of concrete repairs were needed to be
December 11, 2015 Read time: 2 mins
The Canadian built PAM unit was used for the Heathrow Tunnel refurbishment
A Positioner-Actuator-Manipulator (PAM)machine on hire from UK dealer STM of Tring has been able to cut concrete removal time for 3137 Bam Nuttall on its €116.2 million tunnel refurbishment contract at Heathrow Airport. The 18-month contract involves major work on the main and cargo tunnels serving Terminals 1, 2 and 3 in order to comply with the latest European standards and also to extend the life of the tunnels for a further 60 years.

As part of the project, some 206m2 of concrete repairs were needed to be carried out. Bam Nuttall opted to use the Canadian built PAM unit, which allowed work to continue throughout the 10.30 pm to 5.30 am possession time. The breaker is firmly secured to an air-over-hydraulic powered two-piece arm, which isolates vibration from the PAM's controls. The unit is mounted on four castors or removable road wheels and can be pushed into position prior to applying the brake and deploying outrigger legs for stability during operation. Weighing only 525kg without a tool in place, the machine can be easily transported in a conventional van.

For more information on companies in this article

Related Content

  • Well structured maintenance
    January 4, 2013
    Major bridge maintenance and replacement projects across the world are extending the life of many impressive historic landmarks as Guy Woodford reports The Tamar Bridge, part of the main A38 trunk road linking Saltash in Cornwall with Plymouth in Devon, south west England, marked its 50th anniversary with a steel deck resurfacing project involving Stirling Lloyd's Eliminator bridge deck waterproofing system. Jointly owned by Plymouth City Council and Cornwall Council, the Tamar has a suspended length of 642
  • New developments in road recycling and milling
    June 11, 2019
    New developments in road recycling and milling will allow contractors to remove old surfaces more quickly and efficiently – Mike Woof reports
  • Caterpillar’s mini mills offer versatility
    June 28, 2018
    Caterpillar is introducing three new compact milling machines, the PM310, PM312 and PM313, said to combine high performance and versatility. The firm says that its PM300 Series suits use in small-to-medium job sites where compact dimensions, optimum manoeuvrability and high production capabilities are required. The PM300 Series can be configured with one of three drum widths and a choice of wheel or track undercarriage. An articulating right leg can be positioned outboard to provide additional stability du
  • Paving a Japanese airport within strict time constraints
    September 19, 2012
    In Japan, major efforts are being made to both conserve energy and materials, while also delivering high quality airport runways. At Haneda Airport, as well as at the Fukuoka, Chitose and Sendai airports, innovative use is being made of asphalt paving equipment from Sumitomo. The latest model HA60W J paver from Sumitomo is being used to lay warm mix asphalt, while the contractors is also using sophisticated control technology. To minimise disruption to flight schedules, construction work at Haneda has been