Progress on Serbia’s Zezeljev bridge replacement is slow

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp
August 30, 2017 Read time: 2 mins

Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government.

Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported.

The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its campaign against Yugoslavia, of which Serbia was a member. The bridge was damaged first on 20 April 1999 and finally destroyed four days later, according to Edgar Martin, a waterways transportation consultant working in the Balkans.

Construction of the new bridge forms part of an 3287 EU strategy for the Danube Region. The replacement project was delayed initially because of work to remove wreckage of the old bridge in the Danube.

Completion of the bridge is not now likely to be in the spring of next year. Spanish company 5289 Azvi is the contractor and around €30 million of the estimated 60 million has been invested so far.

The minister also expressed concern over slow progress of works on Ub-Obrenovac part of the Corridor 11 motorway.

Serbia’s president Aleksandar Vucichas said he plans to visit the Surcin-Obrenovac section of Corridor 11. China Construction Communication Company began work on the 18km motorway in March 2017, with completion expected by the end of 2019. Value of works is estimated at €208 million, and is financed by China's Exim Bank, while Serbian roads company Putevi Srbije is the investor.

For more information on companies in this article

Related Content

  • Radical routes to highway projects
    March 5, 2012
    The authorities in Poland and Serbia are using innovative approaches to funding highway investments. The Polish Government is considering reallocating savings made on railway tenders to road projects. The Polish Infrastructure Department hopes to transfer some €311 million from its railway programme to road projects instead. This will help deal with the shortfall for highway improvements.
  • IRF Global Road Achievement Awards (GRAA) Winning Project: Morava Corridor Motorway
    April 29, 2025

     

    Bechtel and ENKA each boast rich histories, and together, possess nearly 200 years of combined experience—an impressive feat in today’s competitive landscape. For 35 years, the joint venture has tackled some of the industry’s most challenging motorway projects. The Morava Corridor Motorway Project’s program management exemplifies a commitment to excellence, representing a complex endeavor that few can undertake.  

  • Bosnia gets €750 million loan for Corridor 5C motorway
    March 1, 2018
    Bosnia has signed a European loan agreement worth €750 million for several sections of work on the Corridor 5V motorway project. Denis Zvizdic, head of government for Bosnia and Herzegovina, said the deal was signed in London during a recent investment conference on the western Balkans. Of the loan amount, the Federation of Bosnia and Herzegovina will get €500 million and the internal but autonomous Republika Srpska will receive €250 million. The money will be used for constructing four 70km sections of
  • Germany to cut red tape for bridge construction up to 2027
    October 5, 2017
    The German federal government has set aside €4.5 billion for refurbishment of 400 bridges in the state of North Rhine-Westphalia up to 2027. Hendrik Wüst, North Rhine-Westphalia transport minister, made the announcement which included around €200 million for road maintenance. The Federal German government also plans to fast-track planning for infrastructure projects. Bonuses to contractors for improved performance to reduce down-time on construction sites as well as the possibily of a six-day working