Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Tunnel inspections reveal safety compliance need
    May 9, 2012
    Results show the state of Europe's tunnel infrastructure at its 'most sublime and most depressing quality' as Patrick Smith reports. EuroTAP [European Tunnel Assessment Programme] 2010 has unveiled the results of inspections conducted earlier this year in 26 major tunnels in 13 European countries. The on site inspections, carried out between 12 April and 20 May, 2010, are said to indicate that an "alarming number of operational tunnels across Europe will not be ready to comply with EU tunnel safety rules wh
  • Denmark set to appoint preferred bidder for Fehmarnbelt link
    March 14, 2016
    The Danish political parties behind the Fehmarnbelt link have mandated Femern A/S to appoint preferred bidders for the main tunnel work in order to enter into conditional contracts no later than mid-May. Femern A/S is the Danish government-owned company managing the Fehmarn Belt immersed tunnel project between Denmark and Germany. The project was approved by the Danish parliament in April last year. It is supposed to be built, owned - apart from the German land works - and operated by Femern A/S, a su
  • Golden route to success
    July 20, 2012
    Built in 1937 and still the ninth longest suspension bridge in the world, the Golden Gate Bridge across San Francisco Bay remains in fine shape despite its age - Andrew Bardin Williams writes The Golden Gate Bridge turned 75 years old on May 27 and continues to play a key role in the transportation, engineering, construction and ITS communities. The structure has played an important historical role, an engineering success that boosted the economy of the region. And it also led the way as the first major pub
  • Latin America invests in infrastructure growth
    February 15, 2012
    Travelling in one of the world's most diverse regions is not always easy, but spectacular engineering feats will make life easier as Patrick Smith reports. Five years ago a report from the World Bank noted that infrastructure in most of Latin America and the Caribbean (LAC) had improved over the previous ten years.