Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Australian state government does a deal with East West Connect
    April 15, 2015
    The state government of Victoria in Australia will pay the East West Connect consortium US$258 million to cancel construction of Melbourne’s East West Link road tunnel. The payoff is to cover the consortium's bidding, design and pre-construction costs and draw a line under the deal that has been mired in financial controversy for years. The federal government slammed Victoria’s decision to bail out of the project as “an obscenity’’ that will cost 7000 jobs, according to a report in The Australian news
  • RiverLinx consortium inks London’s Silvertown Tunnel deal
    November 27, 2019
    The RiverLinx consortium has reached financial close on the €1.17 billion Silvertown Tunnel project after a three-year procurement process by the client Transport for London.
  • Mozambique: Maputo cancels Britalar’s Julius Nyerere Avenue deal
    January 14, 2015
    A consortium led by Portuguese contractor Britalar has been sacked from a controversial contract to rehabilitate a prestigious thoroughfare in the Mozambique capital Maputo. The council is seeking repayment of US$1 million from the consortium that includes two other Portuguese companies, Construção Europa Ar-Lindo and Aurélio Martins Sobreiro e Filhos. Media reports also say a Chinese firm has been handed the contract to finish the work that was started in February 2013 under a deal worth $12.5 millio
  • New international trade crossing linking Canada and US
    June 9, 2015
    The Detroit River is short, only 45km, and narrow in places, less than 1km. Around a quarter of the annual $658 billion Canada-US trade crosses over the river. That’s $160 billion worth of goods trucked each year between Detroit in the US state of Michigan and the Canadian city of Windsor in the province of Ontario - the Windsor-Detroit Corridor. There are several types of crossings, but the vast majority of commercial traffic must use the 2.3km Ambassador Bridge (see box). A new bridge was initially prop