Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Australia: Consortium ready to abandon Melbourne’s East West Link
    March 10, 2015
    The East West Connect consortium is set to abandon Melbourne’s East West Link contract in return for a payment of between US$400 million and $535 million, according to media reports. But the Victoria state government is challenging the claim by East West Connect whose partners include Lend Lease, Acciona, Capella Capital and Bouygues. Instead, the government wants East West to payback around $153 million which the consortium allegedly received when the toll road contract was signed, reported the Herald Sun
  • Checking out Europe's motorway service stations
    February 14, 2012
    A survey of a number of Europe's motorway filling stations have thrown up surprising results: some good, some bad. Experts from EuroTest have travelled almost 34,000km to check out 77 filling stations along the most important travel routes in Europe. Keeping a close eye on cameras and staff that might "blow their cover," the results they brought home with them showed that not a single facility [visited] warranted a very good rating.
  • Slovakia’s Cabinet to have final say on D4 Bratislava bypass
    February 9, 2016
    The government of Robert Fico has said it will decide the fate of the controversial €1 billion Bratislava bypass, the D4 motorway project, possibly ahead of a national parliamentary election next month. Fico, who also was prime minister from 2006-2010, was re-appointed after leading his Direction Social Democracy party (SMER-SD) to a landslide victory in the 2012 parliamentary election. His party won 83 seats and formed an absolute majority government, Slovakia’s first since 1989. Controversy continue
  • Interest strong for Colombia key tunnel project
    January 22, 2019
    Interest is strong in the project to complete Colombia’s key tunnel construction contract. In all 23 firms have shown interest in the package of works to complete the La Linea tunnel project, according to the Colombian national road institute (Invias). The Colombian Government is providing US$204.5 million to complete the project. The current target is for the tunnel to be completed by 2020, although the link was originally supposed to be ready for traffic in late 2016. Construction work on the link commenc