Prague wins legal battle over Blanka Tunnel costs

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex. CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.
September 6, 2016 Read time: 2 mins

The Czech capital Prague will not have to pay €63 million to construction firm CKD Praha DIZ for cost overruns on the Blanka Tunnel complex.

CKD Praha DIZ sought the amount over an alleged rise in costs when completion of the tunnel was delayed, according to a report by Radio Praha.

A court of arbitration also ruled that the company must pay the city’s legal costs of around €630,000. The court’s decisions are binding and final.

The 6.4km Blanka Tunnel complex is a part of Prague’s unfinished ring road system and is the longest road tunnel in the Czech Republic and the longest city tunnel in Europe. Just under 40km of the 83km Ring Road are complete.

The tunnel, which connects the area west of Prague Castle with Trója district in the northeast, consists of three tunnels - Bubenečský, Dejvický and Brusnický. Construction started in 2006 and completion was supposed to be 2011.

However, delays put the opening date back to September last year and doubled the overall cost to around €1.6 billion.

A survey by Prague’s Technical Administration of Roadways recently found that on averages 75,000 vehicles use the Blanka tunnel daily.

Related Content

  • Cowi wins Massey Tunnel design
    July 22, 2022
    Cowi has won a contract as owner's engineer for an eight-lane replacement immersed tunnel under the Fraser River near the Pacific coast city of Vancouver. Cowi said it will draw on its experience designing the original four-lane George Massey Tunnel in 1959 and whose removal the engineering firm will later oversee.
  • Meva’s Mammut 350 formwork makes the difference for Neckar viaduct
    April 19, 2018
    Formwork specialist Meva is helping replace the longest motorway bridge, the Neckar River viaduct in Germany’s south-west state Baden-Wuerttemberg Work on the 1.3km Neckar viaduct, part of the A6 motorway at Heilbronn, should be finished by 2022. It is part of the A6 expansion project between the Weinberger junction and Wiesloch/Rauenberg. The project is officially the new Neckar viaduct BAB 6 at Heilbronn. Federal Motorway 6, the A6, is also known as the BAB 6. The 477km motorway starts at the French b
  • Norway drops planned fixed link between Moss and Horten
    October 25, 2018
    Norway’s Road Administration has stopped investigations into a proposed bridge or tunnel spanning 10.5km of the Oslofjord between Moss and Horten, according to Norwegian media. The Ministry of Transport has ordered Veivesendet to cancel consultations amid the government’s growing concern over the cost of any fixed link across the narrows, around 65km south of the capital Oslo. The half-hour car-ferry crossing as part of National Highway 19 will continue as usual. Several thousand people and vehicles m
  • Metrostav/Strabag win Edvard Benes deal
    November 23, 2023
    The €22 million renovation on the bridge over the Elbe in the Czech Republic will start in 2025.