Plan to complete Colombian tunnel project

In Colombia plans are underway to try and revive the project to construct the La Linea tunnel. The project has been beset with problems since work commenced. Problems have included insufficient funding, unexpectedly poor ground conditions and some firms involved having the wrong kind of insurance. The Segundo Centenario consortium is building the La Linea tunnel and is keen for this to continue. The new plan involves the incorporation of local firm Construcciones e Inversiones Beta, which would acquire a 40
December 1, 2014 Read time: 2 mins
In Colombia plans are underway to try and revive the project to construct the La Linea tunnel. The project has been beset with problems since work commenced. Problems have included insufficient funding, unexpectedly poor ground conditions and some firms involved having the wrong kind of insurance. The Segundo Centenario consortium is building the La Linea tunnel and is keen for this to continue. The new plan involves the incorporation of local firm Construcciones e Inversiones Beta, which would acquire a 40% stake in this venture and deliver more capital as required. There are also plans to bring in two new strategic partners, the cement firms Cementos Argos and 3016 Cemex. These companies could offer credit lines for the materials such as cement, concrete and steel to help construct the link. In addition, construction firm Carlos Collins, which is part of the current Segundo Centenario consortium, could transfer funds from the Bogota-Girardot project, in which it also has a stake, into Tunel de la Linea. The consortium has asked for 13 months to complete work on the tunnel, which was originally planned to have opened by November 2014. The investment needed to complete the project has been estimated at US$60 million.

For more information on companies in this article

Related Content

  • Colombia sets out major strategy for highway investment
    January 19, 2015
    International interest is strong in Colombia’s infrastructure expansion. Five foreign firms are competing in the country’s 4G road tender process. Fomento de Construcciones y Contratas (FCC), Sinohydro, Sacyr, Tradeco and ICA are amongst the companies competing for 10 contracts worth some US$5.88 billion. The first project opening for tender on 19th May 2015 will be for the Puerta de Hierro-Carreto-Palmar de Varela and Carreto-Cruz del Viso routes. The final tender documents for the 10 projects are being pu
  • Colombia’s La Linea Tunnel project delayed
    August 22, 2018
    A tale of woe surrounds Colombia’s La Linea Tunnel project, which is still incomplete. The project has been beset by a serious of issues including unexpectedly poor geological conditions, contractors having the wrong kind of insurance, insufficient funds for work to continue and in more recent times, further geological problems. While the Tolima end of the link is now close to completion, work still remains to be done at the Quindio end of the tunnel. Measuring 315m long, the La Gata section is now largely
  • Tunnel for Colombia’s Calarca – Cajamarca Highway
    May 23, 2014
    A new tunnel is forming an important link for a major Colombian highway - Mauro Nogarin reports Work on a major highway project is underway in Colombia, forming part of the Bogota-Buenaventura Corridor. The highway has a length of 503km and is located in central Colombia, connecting the departments of Tolima and Quindio, across the central Andes, with a total cost of around US$330 million. A key section of the project consists of building a unidirectional tunnel of approximately 8.65km in length. Anot
  • Colombia’s troubled tunnel project completion due
    April 26, 2017
    The completion of work on Colombia’s troubled tunnel project is now finally in sight. A new contractor will be selected by Colombia's National Road Institute (Invias) to complete the last section of work required on the La Linea Tunnel. The winner of the tender process will be announced on 13th June 2017. An additional US$50 million is being budgeted by the Colombian authorities to complete the work. It is expected that in all, finishing the project will cost $86.6 million. Work still to be carried out incl