The second span of the New York’s new cable-stayed bridge has now been completed and has opened to traffic. The final span of the Governor Mario M Cuomo Bridge, which replaced the Tappan Zee Bridge, has now been opened to drivers. The opening was delayed slightly due to concerns over the state of a section of the old bridge, now being demolished. The new link was constructed by a joint venture headed by Fluor. With the new bridge opening, all four lanes of eastbound traffic shifted to the new second span. T
September 10, 2018 Read time: 2 mins
New York’s new bridge opening to traffic
The second span of the New York’s new cable-stayed bridge has now been completed and has opened to traffic. The final span of the Governor Mario M Cuomo Bridge, which replaced the Tappan Zee Bridge, has now been opened to drivers. The opening was delayed slightly due to concerns over the state of a section of the old bridge, now being demolished. The new link was constructed by a joint venture headed by 6343 Fluor. With the new bridge opening, all four lanes of eastbound traffic shifted to the new second span. The eastbound span consists of four general purpose traffic lanes, two emergency shoulders, space for a dedicated bus lane and an advanced traffic monitoring system.


The westbound bridge will remain in a temporary configuration while crews complete the bridge’s shared-use path connecting Westchester (New York) and Rockland (New York) counties for pedestrians and cyclists.

The New York State Thruway Authority, in partnership with the Fluor-led joint venture of Tappan Zee Constructors, LLC – comprised of 1021 American Bridge Company, Granite Construction Northeast, Inc. and Taylor Bros., Inc. – replaced the old bridge with a new 5km state-of-the-art, twin-span, cable-stayed bridge crossing the Hudson River between Westchester and Rockland counties. The cable-stayed main span is supported by eight 128m towers, which stand at 5° angles and feature a sleek, chamfered design. The iconic towers support 192 stay cables, which are made up of roughly 7,840km of steel strands.

The Governor Mario M Cuomo Bridge is one of the largest single design-build contracts for a transportation project in the United States and is the largest bridge project in New York state history.

For more information on companies in this article

Related Content

  • First span of Governor Mario M. Cuomo Bridge in New York opens
    August 25, 2017
    The first span of the 5km twin-span Governor Mario M. Cuomo Bridge - formerly the Tappan Zee Bridge - in New York opened August 25. Tappan Zee Constructors, joint venture led by Fluor and including American Bridge, Granite and Taylor Bros., shift all four lanes of westbound traffic from the existing bridge to the new span overnight. The four eastbound lanes will be shifted onto the new span in the autumn. Demolition of the old bridge can then get underway, allowing more room for construction of the adjacent
  • New NY Bridge - Tappan Zee - main span towers poured
    December 16, 2016
    One of the largest US infrastructure projects is nearer completion after recent topping out of the eight main span towers of the New NY Bridge. The final concrete pour was in mid-December and all piles - more than 1,000 - have been installed in Hudson River. To date, 3,000 roadway panels for the approaches - making 5.5km in length - have been installed, according to the New York State Thruway Authority, owner of the New NY Bridge project. The New NY Bridge, also called the Tappan Zee Bridge, is on tra
  • I Lift NY crane places first girder on New York’s Tappan Zee Bridge
    June 25, 2015
    One of the world’s largest cranes has placed the first steel girder assembly for the approach span of the new NY Bridge, often called the Tappen Zee Bridge in New York. The barge-mounted I Lift NY super crane with its nearly 100m boom slowly picked up the 125m unit from its delivery barge and gently lowered it onto concrete pedestals in the Hudson River, near the Rockland County side of the bridge. The super crane will install even larger sections of the new bridge, some of which weigh around 907tonne
  • New York governor aims to freeze Thruway tolls, including Tappaen Zee Bridge
    January 11, 2016
    The governor of the US state New York, Andrew Cuomo, said he wants to spend US$22 billion over the next five year on maintaining aging roads and bridges. Cuomo also wants to give the agency responsible for maintaining the state’s major cross-state tolled freeway, the 920km Thruway, $1 billion so the agency – New York State Thruway Authority - can freeze tolls at their current rate until 2020. US media reported that his plan would also eliminate tolls for agricultural traffic. He would also offer a t