New Wear Crossing cables fully installed and tensioned to 50%

Structural engineering company VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load. The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
September 21, 2017 Read time: 3 mins
Looking good: The 28 cable stays are fully installed on the New Wear Crossing and tensioned to 50 percent.

Structural engineering company 1569 VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load.

The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
 
In the coming months, the temporary supports will be removed, leaving only the single central arched pylon and the bridge deck on display in the river.

Opening of the bridge is expected by spring of next year.

Finishing works, such as road surfacing, paving, lighting, the installation of railings and carrying out road markings, must all be complete before the cable stays can be finely adjusted and locked off at the end of construction.

 The 28 cable stays are installed in pairs north and south of the central pylon. Each cable stay is contained inside a white protective, plastic sheath. Inside each sheath, or tube, are between 44-77 strands, depending on a cable’s intended position on the deck, that form a single cable. They vary in length from 52-165m.

The longer the cable, the more strands there are. Each strand is the diameter of a small coin and will be tensioned to lift seven tonnes.

“People could be forgiven for thinking the bridge is very close to opening as the structure looks complete from a distance,” explained Stephen McCaffrey, project director for 1622 Farrans Construction and Victor Buyck Steel Construction, a joint venture to deliver the project on behalf of Sunderland City Council.

“We still have quite a lot to do, such as completing the road works on both sides of the river, getting the surface of the bridge deck finished and all of those additional works and safety features complete.”
 
Work began on the New Wear Crossing – Sunderland’s first bridge across the River Wear in more than 40 years – in May 2015.

The bridge become more recognisable with the 105m pylon being erected in February, the bridge deck launched across the river in spring and the installation of the cable stays during the summer.

For more information on companies in this article

Related Content

  • A new Indian cable-stayed bridge will improve transport connections
    March 2, 2015
    A major new cable-stayed bridge is being constructed in India - Partha Bratim Basistha reports. In India the construction of a major cable-stayed bridge is underway that will boost connections from capital Delhi to its surrounding areas. The bridge is being built in a bid to ease growing interstate traffic movement between Delhi and the surrounding North Indian states of Punjab, Uttar Pradesh, Haryana and Himachal Pradesh. Named Signature Bridge, this is a landmark structure due to its design aesthetics and
  • Poetry in motion
    August 9, 2018
    A heavy-lift operation by Roll-iT using Enerpac equipment delivered a bridge deck - with a poem engraved on the underside - to Antwerp’s old harbour Only when the deck of the new Londenbrug Bridge is raised do travellers see the poem by Antwerp poet Stijn Vranken. It is written large on the underside of the 300tonne prefabricated steel deck. People waiting for a ship to pass the raised bridge now contemplate the poem’s message about ships transporting goods and people to and from the four corners of the
  • Formwork plays a leading role in global infrastructure projects
    June 13, 2012
    New and highly regarded existing formwork systems have been used in major recent transport-related construction projects across the globe. Guy Woodford looks at some of their applications The multi-million dollar Mississippi River Bridge project in the United State is creating a vital new gateway between Illinois and Missouri. Central to the project is the realignment and reconstruction of Interstate 70 and a new landmark bridge, featuring two pylons projecting vertically from the Mississippi river bed w
  • Washington DC’s historic bridge replacement project
    June 11, 2019
    The project to replace a historic bridge in US capital Washington DC is providing major challenges for its builders - Mike Woof writes