New Wear Crossing cables fully installed and tensioned to 50%

Structural engineering company VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load. The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
September 21, 2017 Read time: 3 mins
Looking good: The 28 cable stays are fully installed on the New Wear Crossing and tensioned to 50 percent.

Structural engineering company 1569 VSL International has installed all 28 cable stays of England’s New Wear Crossing and stressed them to 50% of their design load.

The next stage of stressing the cables will happen next month and be to 100% of design load. This will allow the construction team to adjust and tension them just enough to lift the bridge deck off the blue steel temporary supports that were constructed in the river to take the weight of the structure.
 
In the coming months, the temporary supports will be removed, leaving only the single central arched pylon and the bridge deck on display in the river.

Opening of the bridge is expected by spring of next year.

Finishing works, such as road surfacing, paving, lighting, the installation of railings and carrying out road markings, must all be complete before the cable stays can be finely adjusted and locked off at the end of construction.

 The 28 cable stays are installed in pairs north and south of the central pylon. Each cable stay is contained inside a white protective, plastic sheath. Inside each sheath, or tube, are between 44-77 strands, depending on a cable’s intended position on the deck, that form a single cable. They vary in length from 52-165m.

The longer the cable, the more strands there are. Each strand is the diameter of a small coin and will be tensioned to lift seven tonnes.

“People could be forgiven for thinking the bridge is very close to opening as the structure looks complete from a distance,” explained Stephen McCaffrey, project director for 1622 Farrans Construction and Victor Buyck Steel Construction, a joint venture to deliver the project on behalf of Sunderland City Council.

“We still have quite a lot to do, such as completing the road works on both sides of the river, getting the surface of the bridge deck finished and all of those additional works and safety features complete.”
 
Work began on the New Wear Crossing – Sunderland’s first bridge across the River Wear in more than 40 years – in May 2015.

The bridge become more recognisable with the 105m pylon being erected in February, the bridge deck launched across the river in spring and the installation of the cable stays during the summer.

For more information on companies in this article

Related Content

  • São Paulo's landmark bridge construction
    February 21, 2012
    To improve access from the east to São Paulo city centre, main contractor Construbase Engenharia is building a road complex comprising three viaducts and access ramps. The greatest challenge in Brazil's largest city is the showpiece Padre Adelino viaduct, a 122m long single-arch, single-span, cable-stayed concrete bridge moulded in situ with a parabola-shaped arch and a single-cell post-tensioned cantilever caisson
  • A wheely great bridge for the English city of Hull
    November 6, 2019
    A 60m pre-constructed pedestrian bridge weighing 150 tonnes as been wheeled into position over the A63 in the northern English city of Hull. The covered and vaulted Princess Quays Bridge will be renamed when it opens in the spring enabling pedestrians and cyclists to cross over the busy dual carriageway. The positioning operation meant that first the route was cleared of signage, guardrails and street lights. The bridge was then lowered onto two wheeled transporters – one at each end of the structur
  • Australian bridge slides into position
    July 18, 2012
    A heavy rail crossing as part of Australia's EastLink motorway demanded great ingenuity and careful planning Most of the 88 bridges on the EastLink tolled motorway in, Melbourne, Australia were kept as simple and straightforward as possible. Contractor Thiess John Holland (TJH) developed its own precast yard 150km from the city, which provided many of the prefabricated materials required for the structures. This offered speed and economy while logistics and sequencing were vital for their erection. But the
  • Zipping up road lanes
    September 28, 2018
    QMB has a Lindsay Road Zipper on duty near Montreal. World Highways deputy editor David Arminas climbed aboard As vice president of Canadian barrier specialist QMB, based in Laval, Quebec, Marc-Andre Seguin is sanguine about the future for moveable barriers. On the one hand, it looks good. The oft-stated advantage of moveable barriers is that the systems are cheaper to install than adding a lane or two to a highway or bridge. Directional changes to lanes can boost volume on a road without disrupting tra