New bridge installed in UK over busy rail line

Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridg
January 12, 2016 Read time: 2 mins
Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of 8100 Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridge had to be installed within a tight 76 hour window.

The engineering team included Costain Engineering Services and specialist contractors such as Walters, Freyssinet , Trackwork and SPI Appleton. In order for the installation to be completed within the designated time, the team had to carry out extensive planning beforehand.

The bridge weighed in at just under 4000tonnes and was slid into place using the Autofoncage method, which utilises four large strand jacks. These jacks push the bridge as they pull against the resistance of the strands, which are fixed into the guide raft and a thrust wall.

The team used 3D and 4D Building Information Modelling which allowed them to visualise, plan and share every piece of information with the wider team, clients and stakeholders. In addition to the 4D modelling, the team also completed a Quantative Schedule Risk Assessment, which helped to identify key areas which needed special attention.

No major civil engineering project comes without its challenges and for this project the stability of the old rail embankment caused the biggest hurdle by extending the period the team needed to carefully backfill the structure. The team overcame this challenge and worked closely with Network Rail to manage the completion of the works within the allocated time.

As well as carrying the country’s busiest freight railway line, the new bridge will allow the new highway link to pass underneath it.

For more information on companies in this article

Related Content

  • UK’s A14 route to open early
    February 11, 2020
    Highways England has announced that the UK’s A14 route is to open early.
  • Poetry in motion
    August 9, 2018
    A heavy-lift operation by Roll-iT using Enerpac equipment delivered a bridge deck - with a poem engraved on the underside - to Antwerp’s old harbour Only when the deck of the new Londenbrug Bridge is raised do travellers see the poem by Antwerp poet Stijn Vranken. It is written large on the underside of the 300tonne prefabricated steel deck. People waiting for a ship to pass the raised bridge now contemplate the poem’s message about ships transporting goods and people to and from the four corners of the
  • Revealed: Professionals reveal how they are benefiting from building information modelling
    August 9, 2019
    One of the most important developments in the world of ‘PropTech’ over the last few years has been that of building information modelling (BIM). The technology essentially facilitates architecture, engineering and construction (AEC) professionals to create and use an intelligent 3D model to gain valuable insight into how a building project can be better planned, designed and managed. Interested in ground-breaking ‘PropTech’, housing agents Sellhousefast.uk surveyed 602 architects, engineers and cons
  • Making the U-turn
    August 2, 2012
    Political hostility to a toll road project in Australia has been turned around by the quality and amenity of the project writes Adrian Greeman Cars, trucks and vans were taking to the new EastLink toll road in Melbourne with enthusiasm this July, pleased to try out its 39km route for time and cost savings. As well as the convenience of the uncongested route, drivers were also able to view an extraordinary multi-shaded perspective of transparent green and orange noise wall panels, burnt earth-coloured retai