New bridge installed in UK over busy rail line

Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridg
January 12, 2016 Read time: 2 mins
Work to install a new bridge for the UK’s busiest rail freight line has been carried out over the A160 at the Port of Immingham. The project forms part of the Port of Immingham Improvement Scheme, a €118.15 million (£88.4 million) series of works being carried out on behalf of 8100 Highways England. The project involves upgrading 5km of the A160 from single carriageway to dual carriageway, and constructing a number of new structures. Because of the volume of rail traffic using the stretch of track, the new bridge had to be installed within a tight 76 hour window.

The engineering team included Costain Engineering Services and specialist contractors such as Walters, Freyssinet , Trackwork and SPI Appleton. In order for the installation to be completed within the designated time, the team had to carry out extensive planning beforehand.

The bridge weighed in at just under 4000tonnes and was slid into place using the Autofoncage method, which utilises four large strand jacks. These jacks push the bridge as they pull against the resistance of the strands, which are fixed into the guide raft and a thrust wall.

The team used 3D and 4D Building Information Modelling which allowed them to visualise, plan and share every piece of information with the wider team, clients and stakeholders. In addition to the 4D modelling, the team also completed a Quantative Schedule Risk Assessment, which helped to identify key areas which needed special attention.

No major civil engineering project comes without its challenges and for this project the stability of the old rail embankment caused the biggest hurdle by extending the period the team needed to carefully backfill the structure. The team overcame this challenge and worked closely with Network Rail to manage the completion of the works within the allocated time.

As well as carrying the country’s busiest freight railway line, the new bridge will allow the new highway link to pass underneath it.

For more information on companies in this article

Related Content

  • Bentley advances construction software technology
    December 19, 2016
    Design and construction software specialist Bentley Systems is strengthening its position in the market with the introduction of new software advances as well as a series of strategic business moves. This allows the company to offer new solutions and technologies to its client base, as well as reaching out to new business segments The firm is introducing an array of powerful tools to the market. A key launch is for the OpenRoads Designer CONNECT Edition, which is the successor to Bentley’s well-proven an
  • Scotland’s new Queensferry Crossing over the Forth Estuary
    December 23, 2015
    The new Queensferry Crossing under construction in Scotland will be the third landmark bridge spanning the Forth Estuary - Mike Woof writes When the new Queensferry Crossing over the Forth Estuary opens at the end of 2016, it will be the third landmark bridge to be built spanning this short stretch of water. Lying alongside the existing road bridge and the historic rail bridge, this new structure will be as groundbreaking as the two earlier crossings were at the time of their construction.
  • Motorway's tricky cable installation
    February 6, 2012
    The UK is now benefiting from the installation of sophisticated automated traffic management equipment and information signs on its motorway network. But with heavy traffic volumes on these roads, novel techniques have had to be implemented. One such operation, organised by client The Highways Agency and its consulting engineer A.One+, has recently been underway on the M56 motorway between Junctions 9 and 16 in north-west England under the Triple Package Advanced Works designation. To minimise traffic distu
  • Tampere road tunnel - a strategic link for central Finland
    April 4, 2016
    Progress has been good for an important underground road link in Finland reports Adrian Greeman. Assuming all goes well, the new Ranta, or Lakeside, tunnel in Tampere will open in full six months early; traffic could be running by the end of this year. Work on transforming the rundown city centre with new developments will get a major boost. It is a major achievement on a four-year-long project bringing significant benefits to one of Finland's largest cities. From the government's point of view the scheme w