More financial doubt over proposed Fehmarn Belt Tunnel

The proposed Fehmarn Belt Tunnel to link Denmark and northern Germany will never be economically viable, according a report commissioned by German ferry operator Scandilines. Revenue and traffic forecasts are unrealistically high, notes the report completed by German consultancy DIW Econ. It is unlikely that the latest cost to build the massive road tunnel, around €7.4 billion, would ever be recovered. The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Cur
March 17, 2017 Read time: 2 mins
RSSThe proposed Fehmarn Belt Tunnel to link Denmark and northern Germany will never be economically viable, according a report commissioned by German ferry operator Scandilines.

Revenue and traffic forecasts are unrealistically high, notes the report completed by German consultancy DIW Econ. It is unlikely that the latest cost to build the massive road tunnel, around €7.4 billion, would ever be recovered.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Currently, a ferry connects the two islands. Final planning approval is expected in 2018 with project completion by 2028. But the approval process is currently bogged down over environmental issues being considered by the German state of Schleswig-Holstein in which the southern end of 17km immersed tunnel will surface.

DIW Econ’s 13-page report is based around mathematical calculations of a price war between the ferry and tunnel operators. Tunnel operator Fixed Link has said it will charge around €65 per car and €267 for a truck. The report suggests that the ferry operator will undercut the tunnel operator by half, and take 37% of the car market and retain at least 80% of the truck market.

“This will secure the ferry a decent profit, so that the ferry will stay in the market,” notes the authors. “The report finds that in the baseline scenario the tunnel incurs a loss of at least €3 billion over the 50 years [concession] due to the large market shares captured by the ferry.”

The report says that Fixed Link will make a profit only if the ferry services ceases operations. However, there are variables, acknowledge the authors, and the calculations and results could change with time.

The Danish state-owned company 4782 Femern, which is responsible for designing and planning the project, has dismissed the claims. The project's financial situation is secure according to financial analysis of the project by international auditors on behalf of the Danish Ministry of Transport. Femern also said that the project will be paid off over 36 years as noted by the original plans.

For more information on companies in this article

Related Content

  • Fehmarnbelt Tunnel start looms on the horizon - 2020
    October 20, 2017
    Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company Femern. A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations. Baunkjaer noted that Denmark is all set to p
  • Further delays expected for the Fehmarn Belt Fixed Link
    August 26, 2015
    Further delays to the planned Fehmarn Belt Fixed Link between Germany and Denmark appear likely because of objections to the project during the planning stages, Danish media reported. Government authorities in the German state of Schleswig-Holstein indicated that permission for the project, which focusses on a 17km immersed road and rail tunnel, will probably be given in 2017, and not next year as previously believed. German authorities have received about 3,100 objections to the project that has rise
  • Construction of Fehmarn Belt Link could start in 2019
    February 27, 2018
    Construction of a Fehmarn Belt Link could start a year from now – more than a year ahead of schedule, according to Danish media reports. The timing was put forward by Holger Schou Rasmussen, chairman of Femernbælt Development, and Kristian Pihl Lorenzen, the Liberal Party spokesman for traffic issues. They reportedly said that a pending environmental court case in Germany that has stalled approval by German authorities won’t hold up construction of the 18km crossing as much as had been feared. As late as
  • Fehmarn Fixed Link project finally gets European Commission approval
    March 31, 2020
    EC settles the public financing issue for the Fehmarn project that includes an immersed tunnel.